Montana Code 69-3-714. Criteria for allowable advanced conductor programs
69-3-714. Criteria for allowable advanced conductor programs. (1) The commission may approve cost-effectiveness criteria for advanced conductor projects that may be placed into a utility’s rate base under this part.
Terms Used In Montana Code 69-3-714
- Commission: means the Montana public service commission created in 2-15-2602. See Montana Code 69-3-701
(2)Criteria must be based on established direct current resistance at standard pressure and a temperature of 20 degrees Celsius.
(3)As used in this section, “advanced conductor” means an overhead electricity conductor installed in a transmission or distribution project that has a direct current electrical resistance at least 10% lower than existing conductors of a similar diameter on the system.
(4)In establishing cost-effectiveness criteria, the commission may consider decreased electrical losses and any other relevant consumer, environmental, and system benefits provided by advanced conductors.