In accordance with the schedule established pursuant to ORS § 543A.045, and after conducting the studies and collecting the additional information identified at the public scoping meeting under ORS § 543A.045, the applicant shall prepare an application report and file the report with the Hydroelectric Application Review Team. The application report shall include study results, proposed mitigation measures, applicable state statutes and rules and any necessary changes to the operation of the hydroelectric project required to comply with such statutes and rules. [1997 c.449 § 10]