Idaho Code 42-2813 – Lien Statement — Contents
Current as of: 2023 | Check for updates
|
Other versions
At the earliest practicable time after the letting of the contract for the construction or use of any irrigation or drainage works as herein provided, the auditor of each county affected thereby shall make in tabular form a list and statement showing the following facts and in the order named, viz:
1. The names of the owners of all lands and the names of all public or corporate roads or railroads within their respective counties benefited by the construction of such proposed work as appears from the apportionment of benefits made by the board of county commissioners modified (if at all) by the order of confirmation of the district court.
Terms Used In Idaho Code 42-2813
- Contract: A legal written agreement that becomes binding when signed.
2. The description of said lands as the same appears in such apportionment of benefits so affected, together with the total number of acres in each tract according to the assessment rolls or tax lists of such county.
3. The estimated number of acres benefited in each tract of said land as shown as aforesaid.
4. The amount that each of said tracts of land and that each of said corporate roads or railroads so benefited will be liable for and must pay into the treasury of each county for the said works.