Oregon Statutes 279C.660 – Compensation when contract terminated due to public interest
Current as of: 2023 | Check for updates
|
Other versions
When a public contract is terminated by mutual agreement, provision shall be made for the payment of compensation to the contractor. In addition to a reasonable amount of compensation for preparatory work and for all costs and expenses arising out of termination, the amount to be paid to the contractor:
Terms Used In Oregon Statutes 279C.660
- Contract: A legal written agreement that becomes binding when signed.
(1) Shall be determined on the basis of the contract price in the case of any fully completed separate item or portion of the work for which there is a separate or unit contract price; and
(2) May, with respect to any other work, be a percent of the contract price equal to the percentage of the work completed. [2003 c.794 § 162]