36 CFR 218.8 – Filing an objection
(a) Objections must be filed with the reviewing officer in writing. All objections are available for public inspection during and after the objection process.
(b) Incorporation of documents by reference is not allowed, except for the following list of items that may be referenced by including date, page, and section of the cited document, along with a description of its content and applicability to the objection. All other documents must be included with the objection.
(1) All or any part of a Federal law or regulation.
(2) Forest Service directives and land management plans.
(3) Documents referenced by the Forest Service in the proposed project EA or EIS that is subject to objection.
(4) Comments previously provided to the Forest Service by the objector during public involvement opportunities for the proposed project where written comments were requested by the responsible official.
(c) Issues raised in objections must be based on previously submitted specific written comments regarding the proposed project or activity and attributed to the objector, unless the issue is based on new information that arose after the opportunities for comment. The burden is on the objector to demonstrate compliance with this requirement for objection issues (see paragraph (d)(6) of this section).
(d) At a minimum, an objection must include the following:
(1) Objector’s name and address as defined in § 218.2, with a telephone number, if available;
(2) Signature or other verification of authorship upon request (a scanned signature for electronic mail may be filed with the objection);
(3) When multiple names are listed on an objection, identification of the lead objector as defined in § 218.2. Verification of the identity of the lead objector must be provided upon request or the reviewing officer will designate a lead objector as provided in § 218.5(d);
(4) The name of the proposed project, the name and title of the responsible official, and the name(s) of the national forest(s) and/or ranger district(s) on which the proposed project will be implemented;
(5) A description of those aspects of the proposed project addressed by the objection, including specific issues related to the proposed project; if applicable, how the objector believes the environmental analysis or draft decision specifically violates law, regulation, or policy; suggested remedies that would resolve the objection; supporting reasons for the reviewing officer to consider; and
(6) A statement that demonstrates the connection between prior specific written comments on the particular proposed project or activity and the content of the objection, unless the objection concerns an issue that arose after the designated opportunity(ies) for comment (see paragraph (c) of this section).