43 USC 964 – Limit of time for completion of Colorado and Wyoming pipelines; forfeiture
Current as of: 2024 | Check for updates
|
Other versions
If any section of said pipe line shall not be completed within five years after the location of said section, the right granted in sections 962 to 965 of this title shall be forfeited, as to any incomplete section of said pipe line, to the extent that the same is not completed at the date of the forfeiture.