(a) Managing Costs and Revenues.—Amtrak shall manage its operating costs, pricing policies, and other factors with the goal of having revenues derived each fiscal year from providing intercity rail passenger transportation over the Northeast Corridor route between the District of Columbia and Boston, Massachusetts, equal at least the operating costs of providing that transportation in that fiscal year.
Ask a legal question, get an answer ASAP!
Click here to chat with a lawyer about your rights.
Terms Used In 49 USC 24902
- Deed: The legal instrument used to transfer title in real property from one person to another.
- Fiscal year: The fiscal year is the accounting period for the government. For the federal government, this begins on October 1 and ends on September 30. The fiscal year is designated by the calendar year in which it ends; for example, fiscal year 2006 begins on October 1, 2005 and ends on September 30, 2006.
- Foreclosure: A legal process in which property that is collateral or security for a loan may be sold to help repay the loan when the loan is in default. Source: OCC
- Jurisdiction: (1) The legal authority of a court to hear and decide a case. Concurrent jurisdiction exists when two courts have simultaneous responsibility for the same case. (2) The geographic area over which the court has authority to decide cases.
- Mortgage: The written agreement pledging property to a creditor as collateral for a loan.
- Mortgagee: The person to whom property is mortgaged and who has loaned the money.
- State: means a State, the District of Columbia, the Commonwealth of Puerto Rico, or any other territory or possession of the United States. See 1 USC 7
(b) Priorities in Selecting and Scheduling Projects.—When selecting and scheduling specific projects, Amtrak shall apply the following considerations, in the following order of priority:
(1) Safety-related items should be completed before other items because the safety of the passengers and users of the Northeast Corridor is paramount.
(2) Activities that benefit the greatest number of passengers should be completed before activities involving fewer passengers.
(3) Reliability of intercity rail passenger transportation must be emphasized.
(4) Trip-time requirements of this section must be achieved to the extent compatible with the priorities referred to in paragraphs (1)-(3) of this subsection.
(5) Improvements that will pay for the investment by achieving lower operating or maintenance costs should be carried out before other improvements.
(6) Construction operations should be scheduled so that the fewest possible passengers are inconvenienced, transportation is maintained, and the on-time performance of Northeast Corridor commuter rail passenger and rail freight transportation is optimized.
(7) Planning should focus on completing activities that will provide immediate benefits to users of the Northeast Corridor.
(c) Compatibility With Future Improvements and Production of Maximum Labor Benefits.—Improvements under this section shall be compatible with future improvements in transportation and shall produce the maximum labor benefit from hiring individuals presently unemployed.
(d) Automatic Train Control Systems.—A train operating on the Northeast Corridor main line or between the main line and Atlantic City shall be equipped with an automatic train control system designed to slow or stop the train in response to an external signal.
(e) High-Speed Transportation.—If practicable, Amtrak shall establish intercity rail passenger transportation in the Northeast Corridor that carries out section 703(1)(E) of the Railroad Revitalization and Regulatory Reform Act of 1976 (Public Law 94-210, 90 Stat. 121).
(f) Equipment Development.—Amtrak shall develop economical and reliable equipment compatible with track, operating, and marketing characteristics of the Northeast Corridor, including the capability to meet reliable trip times under section 703(1)(E) of the Railroad Revitalization and Regulatory Reform Act of 1976 (Public Law 94-210, 90 Stat. 121) in regularly scheduled revenue transportation in the Corridor, when the Northeast Corridor improvement program is completed. Amtrak must decide that equipment complies with this subsection before buying equipment with financial assistance of the Government. Amtrak shall submit a request for an authorization of appropriations for production of the equipment.
(g) Agreements for Off-Corridor Routing of Rail Freight Transportation.—(1) Amtrak may make an agreement with a rail freight carrier or a regional transportation authority under which the carrier will carry out an alternate off-corridor routing of rail freight transportation over rail lines in the Northeast Corridor between the District of Columbia and New York metropolitan areas, including intermediate points. The agreement shall be for at least 5 years.
(2) Amtrak shall apply to the Surface Transportation Board for approval of the agreement and all related agreements accompanying the application as soon as the agreement is made. If the Board finds that approval is necessary to carry out this chapter, the Board shall approve the application and related agreements not later than 90 days after receiving the application.
(3) If an agreement is not made under paragraph (1) of this subsection, Amtrak, with the consent of the other parties, may apply to the Surface Transportation Board. Not later than 90 days after the application, the Board shall decide on the terms of an agreement if it decides that doing so is necessary to carry out this chapter. The decision of the Board is binding on the other parties.
(h) Coordination.—(1) The Secretary of Transportation shall coordinate—
(A) transportation programs related to the Northeast Corridor to ensure that the programs are integrated and consistent with the Northeast Corridor improvement program; and
(B) amounts from departments, agencies, and instrumentalities of the Government to achieve urban redevelopment and revitalization in the vicinity of urban rail stations in the Northeast Corridor served by intercity and commuter rail passenger transportation.
(2) If the Secretary finds significant noncompliance with this section, the Secretary may deny financing to a noncomplying program until the noncompliance is corrected.
(i) Completion.—Amtrak shall give the highest priority to completing the program.
(j) Applicable Procedures.—No State or local building, zoning, subdivision, or similar or related law, nor any other State or local law from which a project would be exempt if undertaken by the Federal Government or an agency thereof within a Federal enclave wherein Federal jurisdiction is exclusive, including without limitation with respect to all such laws referenced herein above requirements for permits, actions, approvals or filings, shall apply in connection with the construction, ownership, use, operation, financing, leasing, conveying, mortgaging or enforcing a mortgage of (i) any improvement undertaken by or for the benefit of Amtrak as part of, or in furtherance of, the Northeast Corridor Improvement Project (including without limitation maintenance, service, inspection or similar facilities acquired, constructed or used for high speed trainsets) or chapter 241, 243, or 247 of this title or (ii) any land (and right, title or interest created with respect thereto) on which such improvement is located and adjoining, surrounding or any related land. These exemptions shall remain in effect and be applicable with respect to such land and improvements for the benefit of any mortgagee before, upon and after coming into possession of such improvements or land, any third party purchasers thereof in foreclosure (or through a deed in lieu of foreclosure), and their respective successors and assigns, in each case to the extent the land or improvements are used, or held for use, for railroad purposes or purposes accessory thereto. This subsection shall not apply to any improvement or related land unless Amtrak receives a Federal operating subsidy in the fiscal year in which Amtrak commits to or initiates such improvement.