(a) Authority

Using operation and maintenance funds or facilities and infrastructure funds authorized by a DOE national security authorization, the Secretary of Energy may carry out minor construction projects.

(b) Annual report

Ask a business law question, get an answer ASAP!
Thousands of highly rated, verified business lawyers.
Click here to chat with a lawyer about your rights.

Terms Used In 50 USC 2743

  • Fiscal year: The fiscal year is the accounting period for the government. For the federal government, this begins on October 1 and ends on September 30. The fiscal year is designated by the calendar year in which it ends; for example, fiscal year 2006 begins on October 1, 2005 and ends on September 30, 2006.

The Secretary shall submit to the congressional defense committees on an annual basis a report on each exercise of the authority in subsection (a) during the preceding fiscal year. Each report shall provide a brief description of each minor construction project covered by the report. The report shall include with respect to each project the following:

(1) The estimated original total project cost and the estimated original date of completion.

(2) The percentage of the project that is complete.

(3) The current estimated total project cost and estimated date of completion.

(c) Cost variation reports to congressional committees

If, at any time during the construction of any minor construction project authorized by a DOE national security authorization, the estimated cost of the project is revised and the revised cost of the project exceeds the minor construction threshold, the Secretary shall immediately submit to the congressional defense committees a report explaining the reasons for the cost variation.

(d) Notification required for certain projects

Notwithstanding subsection (a), the Secretary may not start a minor construction project with a total estimated cost of more than $5,000,000 until—

(1) the Secretary notifies the congressional defense committees of such project and total estimated cost; and

(2) a period of 15 days has elapsed after the date on which such notification is received.

(e) Minor construction project defined

In this section, the term “minor construction project” means any plant project not specifically authorized by law for which the approved total estimated cost does not exceed the minor construction threshold.