10 USC 3069 – Buy-to-budget acquisition: end items
(a)
(1) The agency has an established requirement for the end item that is expected to remain substantially unchanged throughout the period of the acquisition.
(2) It is possible to acquire the higher quantity of the end item without additional funding because of production efficiencies or other cost reductions.
(3) The amount of the funds used for the acquisition of the higher quantity of the end item will not exceed the amount provided under that law for the acquisition of the end item.
(4) The amount so provided is sufficient to ensure that each unit of the end item acquired within the higher quantity is fully funded as a complete end item.
(b)
(1) The level of approval within the Department of Defense that is required for a decision to acquire a higher quantity of an end item under subsection (a).
(2) Authority (subject to subsection (a)) to acquire up to 10 percent more than the quantity of an end item approved in a justification and approval of the use of procedures other than competitive procedures for the acquisition of the end item under sections 3201 through 3205 of this title.
(c)
(2) A notification is not required under paragraph (1) if the end item being acquired in a higher quantity is an end item under a tactical missile program or a munitions program.
(d)
(1) specifically refers to this section; and
(2) specifically states that the acquisition of the higher quantity of the end item is prohibited notwithstanding the authority provided in this section.
(e)
(2) In this section:
(A) The term “end item” means a production product assembled, completed, and ready for issue or deployment.
(B) The term “head of an agency” means the Secretary of Defense, the Secretary of the Army, the Secretary of the Navy, and the Secretary of the Air Force.