Florida Regulations 1A-31.055: Notice of Approval or Denial
Current as of: 2024 | Check for updates
|
Other versions
(1) The division shall notify the applicant of approval or intended denial of the application at the address provided in the application or as specified in any notice of change, per Fl. Admin. Code R. 1A-31.080,within 90 days after receipt by the division of a completed application for a permit or a permit renewal. If the application is approved, the division shall furnish a permit document for signature by the applicant certifying agreement with its terms and conditions. The applicant shall return the signed permit to the division for signature by the division’s authorized representative. The permit shall be executed by the division and returned to the permittee within 15 days of receipt. The permit is effective when it is signed by the applicant and the division.
Rulemaking Authority Florida Statutes § 267.031(1). Law Implemented 267.031(2) FS. History-New 7-20-09.
(2) If the division intends to deny the application, the division shall list those criteria from
Fl. Admin. Code R. 1A-31.046, on which the intended denial is based and inform the applicant of the options available within the 90 days as cited above.
Rulemaking Authority Florida Statutes § 267.031(1). Law Implemented 267.031(2) FS. History-New 7-20-09.