(a) A local publicly owned electric utility shall make appropriate space and capacity on and in a utility pole and support structure owned or controlled by the local publicly owned electric utility available for use by a communications service provider pursuant to reasonable terms and conditions. Rates, terms, and conditions that are specified in a contract executed before January 1, 2012, shall remain valid until the contract, rate, term, or condition expires or is terminated according to its terms by one of the parties. If an annual fee is included in a contract executed before January 1, 2012, but the amount of the fee is left unspecified, the requirements of Section 9512 apply.

(b) (1) A local publicly owned electric utility shall respond to a request for use by a communications service provider of a utility pole or support structure owned or controlled by the local publicly owned electric utility within 45 days of the date of receipt of the request, or 60 days if the request is to attach to over 300 poles. If the request is denied, the local publicly owned electric utility shall provide in the response the reason for the denial and the remedy to gain access to the utility pole or support structure. If a request to attach is accepted, the local publicly owned electric utility, within 14 days after acceptance of the request, shall provide a cost estimate, based on actual cost, for any necessary make-ready work required to accommodate the attachment. The requesting party shall accept or reject the make-ready cost estimate within 14 days. Within 60 days of acceptance of the cost estimate, the local publicly owned electric utility shall notify any existing third-party attachers that make-ready work for a new attacher needs to be performed. The requesting party shall have the responsibility to coordinate with third-party existing attachers for make-ready work to be completed. All parties shall complete all make-ready work within 60 days of the notice, or within 105 days in the case of a request to attach to over 300 poles. The local publicly owned electric utility may complete make-ready work without the consent of the existing attachers, if the existing attachers fail to move their attachments by the end of the make-ready timeline requirements specified in this paragraph.

Ask a business law question, get an answer ASAP!
Thousands of highly rated, verified business lawyers.
Click here to chat with a lawyer about your rights.

Terms Used In California Public Utilities Code 9511

  • Attachment: A procedure by which a person's property is seized to pay judgments levied by the court.
  • Communications service provider: means a cable television corporation, video service provider, or telephone corporation. See California Public Utilities Code 9510.5
  • Contract: A legal written agreement that becomes binding when signed.
  • Utility pole: means an electricity or telephone pole, but does not include a street light pole or an electricity pole used solely for the transmission of electricity at 50 kilovolts or higher and not intended for distribution of communications signals or electricity at lower voltages. See California Public Utilities Code 9510.5

(2) The timelines described in paragraph (1) may be extended under special circumstances upon agreement of the local publicly owned electric utility and the communications service provider.

(c) A local publicly owned electric utility may deny an application for use of a utility pole or support structure because of insufficient capacity or safety, reliability, or engineering concerns. In denying an application, a local publicly owned electric utility may also take into account the manner in which a request from a communications service provider under this part could impact an approved project for future use by the local publicly owned electric utility of its utility poles or support structures for delivery of its core utility service.

(d) This part does not limit the authority of a local publicly owned electric utility to ensure compliance with all applicable provisions of law in determining whether to approve or disapprove use of a utility pole or support structure.

(Added by Stats. 2011, Ch. 580, Sec. 2. (AB 1027) Effective January 1, 2012.)