(A) At any time within the period allowed an operator by section 1514.02 of the Revised Code to reclaim an area of land affected by surface or in-stream mining, the operator may file a request, on a form provided by the chief of the division of mineral resources management, for inspection of the area of land upon which the reclamation, other than any required planting, is completed. The request shall include all of the following:

Ask a business law question, get an answer ASAP!
Thousands of highly rated, verified business lawyers.
Click here to chat with a lawyer about your rights.

Terms Used In Ohio Code 1514.05

  • Another: when used to designate the owner of property which is the subject of an offense, includes not only natural persons but also every other owner of property. See Ohio Code 1.02
  • Area of land affected: means the area of land that has been excavated, or upon which a spoil bank exists, or both. See Ohio Code 1514.01
  • Bond: includes an undertaking. See Ohio Code 1.02
  • in writing: includes any representation of words, letters, symbols, or figures; this provision does not affect any law relating to signatures. See Ohio Code 1.59
  • In-stream mining: means all or any part of a process followed in the production of minerals from the bottom of the channel of a watercourse that drains a surface area of more than one hundred square miles. See Ohio Code 1514.01
  • Obligation: An order placed, contract awarded, service received, or similar transaction during a given period that will require payments during the same or a future period.
  • Operator: means any person engaged in surface mining who removes minerals, or minerals and incidental coal, from the earth by surface mining or who removes overburden for the purpose of determining the location, quality, or quantity of a mineral deposit. See Ohio Code 1514.01
  • Performance bond: means the surety bond required to be filed under section 1514. See Ohio Code 1514.01
  • Property: means real and personal property. See Ohio Code 1.59
  • state: means the state of Ohio. See Ohio Code 1.59
  • Surface mining: means all or any part of a process followed in the production of minerals from the earth or from the surface of the land by surface excavation methods, such as open pit mining, dredging, placering, or quarrying, and includes the removal of overburden for the purpose of determining the location, quantity, or quality of mineral deposits, and the incidental removal of coal at a rate less than one-sixth the total weight of minerals and coal removed during the year, but does not include: test or exploration boring; mining operations carried out beneath the surface by means of shafts, tunnels, or similar mine openings; the extraction of minerals, other than coal, by a landowner for the landowner's own noncommercial use where such material is extracted and used in an unprocessed form on the same tract of land; the extraction of minerals, other than coal, from borrow pits for highway construction purposes, provided that the extraction is performed under a bond, a contract, and specifications that substantially provide for and require reclamation practices consistent with the requirements of this chapter; the removal of minerals incidental to construction work, provided that the owner or person having control of the land upon which the construction occurs, the contractor, or the construction firm possesses a valid building permit; the removal of minerals to a depth of not more than five feet, measured from the highest original surface elevation of the area to be excavated, where not more than one acre of land is excavated during twelve successive calendar months; routine dredging of a watercourse for purely navigational or flood control purposes during which materials are removed for noncommercial purposes, including activities conducted by or on behalf of a conservancy district, organized under Chapter 6101. See Ohio Code 1514.01

(1) The location of the area and number of acres;

(2) The permit number;

(3) A map showing the location of the acres reclaimed, prepared and certified in accordance with division (A)(11) or (12) of section 1514.02 of the Revised Code, as appropriate. In the case of an in-stream mining operation, the map also shall include, as applicable, the information required under division (A)(18) of section 1514.02 of the Revised Code.

The chief shall make an inspection and evaluation of the reclamation of the area of land for which the request was submitted within ninety days after receipt of the request or, if the operator fails to complete the reclamation or file the request as required, as soon as the chief learns of the default. Thereupon, if the chief approves the reclamation, other than any required planting, as meeting the requirements of this chapter, rules adopted thereunder, any orders issued during the mining or reclamation, and the specifications of the plan for mining and reclaiming, the chief shall issue an order to the operator and the operator’s surety releasing them from liability for one-half of the total amount of their surety bond on deposit to ensure reclamation for the area upon which reclamation is completed. If the operator has deposited cash, an irrevocable letter of credit, or certificates of deposit in lieu of a surety bond to ensure reclamation, the chief shall deliver to the operator or the operator’s authorized agent one-half of the amount so held.

If the chief does not approve the reclamation, other than any required planting, the chief shall notify the operator by certified mail. The notice shall be an order stating the reasons for unacceptability, ordering further actions to be taken, and setting a time limit for compliance. If the operator does not comply with the order within the time limit specified, the chief may order an extension of time for compliance after determining that the operator’s noncompliance is for good cause, resulting from developments partially or wholly beyond the operator’s control. If the operator complies within the time limit or the extension of time granted for compliance, the chief shall order release of the performance bond in the same manner as in the case of approval of reclamation, other than any required planting, by the chief, and the chief shall proceed as in that case. If the operator does not comply within the time limit and the chief does not order an extension, or if the chief orders an extension of time and the operator does not comply within the extension of time granted for compliance, the chief shall issue another order declaring that the operator has failed to reclaim and, if the operator’s permit has not already expired or been revoked, revoking the operator’s permit. The chief shall thereupon proceed under division (C) of this section.

(B) At any time within the period allowed an operator by section 1514.02 of the Revised Code to reclaim an area affected by surface mining, the operator may file a request, on a form provided by the chief, for inspection of the area of land on which all reclamation, including the successful establishment of any required planting, is completed. The request shall include all of the following:

(1) The location of the area and number of acres;

(2) The permit number;

(3) The type and date of any required planting of vegetative cover and the degree of success of growth;

(4) A map showing the location of the acres reclaimed, prepared and certified in accordance with division (A)(11) or (12) of section 1514.02 of the Revised Code, as appropriate. In the case of an in-stream mining operation, the map also shall include the information required under division (A)(18) of section 1514.02 of the Revised Code.

The chief shall make an inspection and evaluation of the reclamation of the area of land for which the request was submitted within ninety days after receipt of the request or, if the operator fails to complete the reclamation or file the request as required, as soon as the chief learns of the default. Thereupon, if the chief finds that the reclamation meets the requirements of this chapter, rules adopted under it, any orders issued during the mining and reclamation, and the specifications of the plan for mining and reclaiming and decides to release any remaining performance bond on deposit to ensure reclamation of the area on which reclamation is completed, within ten days of completing the inspection and evaluation, the chief shall order release of the remaining performance bond in the same manner as in the case of approval of reclamation other than required planting, and the chief shall proceed as in that case.

If the chief does not approve the reclamation performed by the operator, the chief shall notify the operator by certified mail within ninety days of the filing of the application for inspection or of the date when the chief learns of the default. The notice shall be an order stating the reasons for unacceptability, ordering further actions to be taken, and setting a time limit for compliance. If the operator does not comply with the order within the time limit specified, the chief may order an extension of time for compliance after determining that the operator’s noncompliance is for good cause, resulting from developments partially or wholly beyond the operator’s control. If the operator complies within the time limit or the extension of time granted for compliance, the chief shall order release of the remaining performance bond in the same manner as in the case of approval of reclamation by the chief, and the chief shall proceed as in that case. If the operator does not comply within the time limit and the chief does not order an extension, or if the chief orders an extension of time and the operator does not comply within the extension of time granted for compliance, the chief shall issue another order declaring that the operator has failed to reclaim and, if the operator’s permit has not already expired or been revoked, revoking the operator’s permit. The chief then shall proceed under division (C) of this section.

(C) Upon issuing an order under division (A) or (B) of this section declaring that the operator has failed to reclaim, the chief shall make a finding as to the number and location of the acres of land that the operator has failed to reclaim in the manner required by this chapter. The chief shall order the release of the performance bond in the amount of five hundred dollars per acre for those acres that the chief finds to have been reclaimed in the manner required by this chapter. The release shall be ordered in the same manner as in the case of other approval of reclamation by the chief, and the chief shall proceed as in that case. If the operator has on deposit cash, an irrevocable letter of credit, or certificates of deposit to ensure reclamation of the area of the land affected, the chief at the same time shall issue an order declaring that the remaining cash, irrevocable letter of credit, or certificates of deposit are the property of the state and are available for use by the chief in performing reclamation of the area and shall proceed in accordance with section 1514.06 of the Revised Code.

If the operator has on deposit a surety bond to ensure reclamation of the area of land affected, the chief shall notify the surety in writing of the operator’s default and shall request the surety to perform the surety’s obligation and that of the operator. The surety, within ten days after receipt of the notice, shall notify the chief as to whether it intends to perform those obligations.

If the surety chooses to perform, it shall arrange for work to begin within thirty days of the day on which it notifies the chief of its decision. If the surety completes the work as required by this chapter, the chief shall issue an order to the surety releasing the surety from liability under the bond in the same manner as if the surety were an operator proceeding under this section. If, after the surety begins the work, the chief determines that the surety is not carrying the work forward with reasonable progress, or that it is improperly performing the work, or that it has abandoned the work or otherwise failed to perform its obligation and that of the operator, the chief shall issue an order terminating the right of the surety to perform the work and demanding payment of the amount due as required by this chapter.

If the surety chooses not to perform and so notifies the chief, does not respond to the chief’s notice within ten days of receipt thereof, or fails to begin work within thirty days of the day it timely notifies the chief of its decision to perform its obligation and that of the operator, the chief shall issue an order terminating the right of the surety to perform the work and demanding payment of the amount due, as required by this chapter.

Upon receipt of an order of the chief demanding payment of the amount due, the surety immediately shall deposit with the chief cash in the full amount due under the order for deposit with the chief. If the surety fails to make an immediate deposit, the chief shall certify it to the attorney general for collection. When the chief has issued an order terminating the right of the surety and has the cash on deposit, the cash is the property of the state and is available for use by the chief, who shall proceed in accordance with section 1514.06 of the Revised Code.