Ohio Code 4928.643 – Baselines for compliance with qualified renewable energy resource requirements
(A) Except as provided in division (B) of this section and section 4928.644 of the Revised Code, the baseline for an electric distribution utility‘s or an electric services company’s compliance with the qualified renewable energy resource requirements of section 4928.64 of the Revised Code shall be the average of total kilowatt hours sold by the utility or company in the preceding three calendar years to the following:
Terms Used In Ohio Code 4928.643
- Baseline: Projection of the receipts, outlays, and other budget amounts that would ensue in the future without any change in existing policy. Baseline projections are used to gauge the extent to which proposed legislation, if enacted into law, would alter current spending and revenue levels.
- Certified territory: means the certified territory established for an electric supplier under sections 4933. See Ohio Code 4928.01
- Electric distribution utility: means an electric utility that supplies at least retail electric distribution service. See Ohio Code 4928.01
- Electric services company: includes a power marketer, power broker, aggregator, or independent power producer but excludes an electric cooperative, municipal electric utility, governmental aggregator, or billing and collection agent. See Ohio Code 4928.01
- Renewable energy resource: includes , but is not limited to, any fuel cell used in the generation of electricity, including, but not limited to, a proton exchange membrane fuel cell, phosphoric acid fuel cell, molten carbonate fuel cell, or solid oxide fuel cell; wind turbine located in the state's territorial waters of Lake Erie; methane gas emitted from an abandoned coal mine; waste energy recovery system placed into service or retrofitted on or after the effective date of the amendment of this section by…. See Ohio Code 4928.01
- state: means the state of Ohio. See Ohio Code 1.59
(1) In the case of an electric distribution utility, any and all retail electric consumers whose electric load centers are served by that utility and are located within the utility’s certified territory;
(2) In the case of an electric services company, any and all retail electric consumers who are served by the company and are located within this state.
(B) Beginning with compliance year 2014, a utility or company may choose for its baseline for compliance with the qualified renewable energy resource requirements of section 4928.64 of the Revised Code to be the total kilowatt hours sold to the applicable consumers, as described in division (A)(1) or (2) of this section, in the applicable compliance year.
(C) A utility or company that uses the baseline permitted under division (B) of this section may use the baseline described in division (A) of this section in any subsequent compliance year. A utility or company that makes this switch shall use the baseline described in division (A) of this section for at least three consecutive compliance years before again using the baseline permitted under division (B) of this section.