New Jersey Statutes 52:27D-131. Construction permits; application, approval, expiration, cancellation, extension
Terms Used In New Jersey Statutes 52:27D-131
- Appeal: A request made after a trial, asking another court (usually the court of appeals) to decide whether the trial was conducted properly. To make such a request is "to appeal" or "to take an appeal." One who appeals is called the appellant.
- Mortgagee: The person to whom property is mortgaged and who has loaned the money.
The commissioner, after consultation with the code advisory board, may, for certain classes or types of occupancy posing special or unusual hazards to public safety, establish regulations designating the department as the enforcing agency for purposes of approving plans and specifications. A municipal enforcing agency shall not grant an occupancy permit for any such class or type of construction unless the applicant submits appropriate plans and specifications certified or approved by the department. Upon submission by an applicant of such certified approved plans and specifications, the enforcing agency shall recognize the approval when deciding whether to approve the application for a construction permit.
b. A construction permit, issued in accordance with the foregoing provisions, pursuant to which no construction has been undertaken above the foundation walls within one year from the time of issuance, shall expire.
c. The enforcing agency may revoke or cancel a construction permit in the event the project for which the permit is obtained is not completed by the third anniversary of the date of issuance of the construction permit. Notwithstanding the provisions of any other law, rule or regulation to the contrary, the enforcing agency may revoke or cancel a construction permit in effect on the effective date of P.L.2001, c.457 (C. 52:27D-131.1 et al.), if the project for which the construction permit was obtained is not completed by the third anniversary of the effective date of P.L.2001, c.457 (C. 52:27D-131.1 et al.).
d. If the project for which the permit is obtained is not completed by a deadline set forth in this section, the permittee may submit a request for an extension of the permit to the enforcing agency for review. The enforcing agency may extend the permit for a period of one year. Approval of the extension shall not be unreasonably withheld. Denial of a request for an extension may be appealed to the county construction board of appeals established pursuant to section 9 of P.L.1975, c.217 (C. 52:27D-127). If a project is not completed within the deadline set forth in this section, the enforcing agency shall take all appropriate action up to and including demolition of the uncompleted structure.
The provisions of this subsection shall not apply to a permit obtained: (1) to construct improvements to the interior of a residential property in which the permittee is currently residing that are not visible from the outside of the residential property, (2) for any building of which the exterior and all required site improvements have been fully constructed, or (3) for a project while that project is under the control of a mortgagee in possession.
The enforcing agency may suspend, revoke or cancel a construction permit in case of neglect or failure to comply with the provisions of this act or the code, or upon a finding by it that a false statement or representation has been made in the application for the construction permit.
L.1975, c.217, s.13; amended 2001, c.457, s.1; 2015, c.159, s.1.