Utah Code 73-26-502. Analysis of benefits and costs — Allocation of costs
Current as of: 2024 | Check for updates
|
Other versions
The division shall:
(1) identify the uses and calculate the economic benefits and costs of the developed water; and
Terms Used In Utah Code 73-26-502
- Division: means the Division of Water Resources. See Utah Code 73-26-103
- Project costs: include preconstruction costs, construction costs, environmental mitigation costs, and costs of operation, maintenance, repair, and replacement. See Utah Code 73-26-103
(2) allocate project costs according to the following purposes:
(2)(a) municipal and industrial;
(2)(b) agricultural;
(2)(c) hydropower;
(2)(d) recreation;
(2)(e) fish and wildlife; and
(2)(f) flood control.