Indiana Code 8-1-40-19. Electricity supplier’s petition to commission for recovery of energy delivery costs attributable to distributed generation customers; approval; findings by commission
Current as of: 2024 | Check for updates
|
Other versions
Sec. 19. (a) To ensure that customers that produce distributed generation are properly charged for the costs of the electricity delivery system through which an electricity supplier:
(2) procures excess distributed generation from those customers;
(1) provides retail electric service to those customers; and
Terms Used In Indiana Code 8-1-40-19
- commission: refers to the Indiana utility regulatory commission created by IC 8-1-1-2. See Indiana Code 8-1-40-1
- distributed generation: means electricity produced by a generator or other device that is:
Indiana Code 8-1-40-3
- electricity supplier: means a public utility (as defined in IC 8-1-2-1) that furnishes retail electric service to customers in Indiana. See Indiana Code 8-1-40-4
- excess distributed generation: means the difference between:
Indiana Code 8-1-40-5
the electricity supplier may request approval by the commission of the recovery of energy delivery costs attributable to serving customers that produce distributed generation.
(b) The commission may approve a request for cost recovery submitted by an electricity supplier under subsection (a) if the commission finds that the request:
(1) is reasonable; and
(2) does not result in a double recovery of energy delivery costs from customers that produce distributed generation.
As added by P.L.264-2017, SEC.6.