Indiana Code 8-1-42-19. CSE system’s failure to generate electricity; presumed abandonment; required removal of project assets; project owner’s failure to remove assets; removal of assets by permit authority; recovery of costs
(1) the CSE system is considered abandoned as of the date that is five hundred forty (540) days after the date on which the CSE system last generated electricity; and
Terms Used In Indiana Code 8-1-42-19
- Assets: (1) The property comprising the estate of a deceased person, or (2) the property in a trust account.
- CSE system: means a system that:
Indiana Code 8-1-42-2
- permit authority: means :
Indiana Code 8-1-42-6
- project owner: means a person that:
Indiana Code 8-1-42-7
- unit: refers to :
Indiana Code 8-1-42-8
- Year: means a calendar year, unless otherwise expressed. See Indiana Code 1-1-4-5
(b) In the case of abandonment, as described in subsection (a), if the project owner fails to remove the CSE system project assets not later than one (1) year after the date of abandonment, as required by subsection (a)(2), the permit authority may engage qualified contractors to:
(1) enter the project site;
(2) remove the CSE system project assets;
(3) sell any assets removed; and
(4) remediate the site;
and may initiate proceedings to recover any costs incurred.
As added by P.L.90-2022, SEC.2.