1.  No contract for doing construction work for acquiring or improving the project contemplated may be made or awarded, nor may the governing body incur any expense or liability in relation thereto, except for maps, plats, diagrams, estimates, plans, specifications and notices, until after the hearing upon the provisional order and notice thereof provided for in NRS 271.305 have been given and had.

Ask a legal question, get an answer ASAP!
Click here to chat with a lawyer about your rights.

Terms Used In Nevada Revised Statutes 271.335

  • Contract: A legal written agreement that becomes binding when signed.
  • person: means a natural person, any form of business or social organization and any other nongovernmental legal entity including, but not limited to, a corporation, partnership, association, trust or unincorporated organization. See Nevada Revised Statutes 0.039
  • Remainder: An interest in property that takes effect in the future at a specified time or after the occurrence of some event, such as the death of a life tenant.

2.  This section does not prevent the governing body from advertising by publication for proposals for doing the work whenever the governing body sees fit, but the contract may not be made or awarded before the time stated in subsection 1.

3.  Except as otherwise provided in subsection 12 and in NRS 271.800, in the case of construction work done by independent contract for any project, or portion thereof, in any improvement district, the municipality shall request competitive bids, and proceed thereon, pursuant to the provisions of chapter 338 of NRS.

4.  The municipality may waive any irregularity in the form of any bid.

5.  Any contract may be let on a lump sum or on a unit basis.

6.  No contract may be entered into for such work unless the contractor gives an undertaking with a sufficient surety or sureties approved by the governing body and in an amount fixed by it for the faithful performance of the contract and for payment of the contract.

7.  Upon default in the performance of any contract, any designated official, as directed by motion of the governing body, may advertise and relet the remainder of the work without further ordinance or resolution and deduct the cost from the original contract price and recover any excess cost by suit on the original bond, or otherwise.

8.  All contracts must provide among other things that the person entering into the contract with the municipality will pay for all materials furnished and labor and services rendered for the performance of the contract, and that any person furnishing the materials or rendering the services may maintain an action to recover for them against the obligor in the undertaking as though the person was named therein.

9.  A contract or agreement made in violation of the provisions of this section is voidable, and no action may be maintained thereon by any party thereto against the municipality.

10.  To the extent the municipality makes any payment thereunder, such a contract or agreement is valid, and any such payment may be included in any cost defrayed by the levy of assessments, unless theretofore the municipality elects to void the contract or agreement in its entirety and to recover any such payment from the party to whom made.

11.  The governing body, except as expressly limited in this section, may, in the letting of contracts, impose such conditions upon bidders with regard to bonds and securities, and such guaranties of good and faithful performance and completion of any work and the keeping of the work in repair, and providing for any further matter or thing in connection therewith, as may be considered by the governing body to be advantageous to the municipality and to all interested.