Florida Statutes 378.209 – Timing of reclamation
Current as of: 2024 | Check for updates
|
Other versions
(1) Reclamation should be completed within 2 years after the completion of mining operations, exclusive of a growing season required to ensure establishment of vegetation. For purposes of this section, completion of reclamation occurs when initial revegetation is completed and not at the time of final release of the reclamation area. For the purpose of s. 378.208, the schedule for complete reclamation is as prescribed in paragraphs (a)-(e).
(a) For the period July 1, 1975, to December 31, 1980, for existing mines or the first 5-year period of mining for new mines, reclamation may not be required, and any reclamation that is completed must be credited forward.
Terms Used In Florida Statutes 378.209
- Acres mined: means all acres on which mining operations have resulted in extraction of phosphate rock. See Florida Statutes 378.203
- Department: means the Department of Environmental Protection. See Florida Statutes 378.203
- Mining operations: means those physical activities, other than prospecting and site preparation, which are necessary for extraction, waste disposal, storage, or dam maintenance prior to abandonment. See Florida Statutes 378.203
- operator: includes a parent, its subsidiary, or division. See Florida Statutes 378.203
- Reclamation: means the reshaping of lands in a manner that meets the reclamation criteria and standards contained in this part. See Florida Statutes 378.203
- Revegetation: means , in reclaimed areas, a cover of vegetation consistent with the criteria and standards established pursuant to this part and consistent with the land form created and the future land uses. See Florida Statutes 378.203
(b) For the period January 1, 1981, to December 31, 1985, for existing mines or the second 5-year period of mining for new mines, reclamation of acres mined must be completed at the rate of an acreage equivalent of 15 percent of the acres mined during the period July 1, 1975, to December 31, 1980, or the immediately preceding 5-year period, as appropriate. Reclamation in excess of the required percentage must be credited forward.
(c) For the period January 1, 1986, to December 31, 1990, for existing mines or the third 5-year period of mining for new mines, reclamation of acres mined must be completed at the rate of an acreage equivalent of 60 percent of the acres mined during the period January 1, 1981, to December 31, 1985, or the immediately preceding 5-year period, as appropriate. Reclamation in excess of the required percentage must be credited forward.
(d) For the period January 1, 1991, to December 31, 1995, for existing mines or the fourth 5-year period of mining for new mines, reclamation of acres mined must be completed at the rate of an acreage equivalent of 75 percent of the acres mined during the period January 1, 1986, to December 31, 1990, or the immediately preceding 5-year period, as appropriate. Reclamation in excess of the required percentage must be credited forward.
(e) For the period January 1, 1996, to December 31, 2000, for existing mines or the fifth 5-year period of mining for new mines, and each 5-year period thereafter, reclamation of acres mined must be completed at the rate of an acreage equivalent of 100 percent of acres mined during the immediately preceding 5-year period. Reclamation in excess of the required percentage must be credited forward.
(2) The rate of mining during any 5-year period is to be determined solely by the operator and not the state.
(3) The time periods and reclamation rates specified in this section may be modified or waived for experimental reclamation programs, to take into account the effect of temporary shutdown of mining operations or other physical restraints, for unreasonable delays in the processing of reclamation applications by the department, or to relieve or prevent extreme economic hardship on the operator.
(4) When the beneficial use of a constructed clay settling area has been extended, the rate of reclamation requirements in paragraphs (1)(a)-(e) and the requirements of s. 378.208 apply to such settling area when the beneficial use of such settling area is completed.