Virginia Code 15.2-2209.1:2: Extension of land use approvals for solar photovoltaic projects.
A. An initial approval of a special exception, special use permit, or conditional use permit for a solar photovoltaic or energy storage project shall provide the landowner or developer a minimum of three years to commence the project.
Terms Used In Virginia Code 15.2-2209.1:2
- Amendment: A proposal to alter the text of a pending bill or other measure by striking out some of it, by inserting new language, or both. Before an amendment becomes part of the measure, thelegislature must agree to it.
- Development: means a tract of land developed or to be developed as a unit under single ownership or unified control which is to be used for any business or industrial purpose or is to contain three or more residential dwelling units. See Virginia Code 15.2-2201
- Fraud: Intentional deception resulting in injury to another.
- Governing body: means the board of supervisors of a county, council of a city, or council of a town, as the context may require. See Virginia Code 15.2-102
- Locality: means a county, city, or town as the context may require. See Virginia Code 1-221
- Special exception: means a special use that is a use not permitted in a particular district except by a special use permit granted under the provisions of this chapter and any zoning ordinances adopted herewith. See Virginia Code 15.2-2201
- State: when applied to a part of the United States, includes any of the 50 states, the District of Columbia, the Commonwealth of Puerto Rico, Guam, the Northern Mariana Islands, and the United States Virgin Islands. See Virginia Code 1-245
For so long as the special exception, special use permit, or conditional use permit remains valid, no change or amendment to any local ordinance, map, resolution, rule, regulation, policy, or plan adopted subsequent to the date of approval of the special exception, special use permit, or conditional use permit shall adversely affect the right of the developer or his successor in interest to commence and complete an approved development in accordance with the lawful terms of the special exception, special use permit, or conditional use permit unless the change or amendment is required to comply with state law or there has been a mistake, fraud, or a change in circumstances substantially affecting the public health, safety, or welfare.
Application for minor modifications to special exceptions, special use permits, or conditional use permits made during the period of validity shall not constitute a waiver of the provisions hereof nor shall the approval of minor modifications extend the period of validity of such plats or plans.
B. Notwithstanding any other provision of this chapter, for any valid special exception, special use permit, or conditional use permit, or any modifications thereto, for a solar photovoltaic or energy storage project outstanding as of July 1, 2023, any deadline in the exception permit, or in the local zoning ordinance that requires the landowner or developer to commence the project within a certain time, may be extended by a resolution of the governing body until July 1, 2026, or such longer period as may be agreed to by the locality.