10 CFR 2.340 – Initial decision in certain contested proceedings; immediate effectiveness of initial decisions; issuance of authorizations, permits, and licenses
(a) Initial decision—production or utilization facility operating license. (1) Matters in controversy; presiding officer consideration of matters not put in controversy by parties. In any initial decision in a contested proceeding on an application for an operating license or renewed license (including an amendment to or renewal of an operating license or renewed license) for a production or utilization facility, the presiding officer shall make findings of fact and conclusions of law on the matters put into controversy by the parties and any matter designated by the Commission to be decided by the presiding officer. The presiding officer shall also make findings of fact and conclusions of law on any matter not put into controversy by the parties, but only to the extent that the presiding officer determines that a serious safety, environmental, or common defense and security matter exists, and the Commission approves of an examination of and decision on the matter upon its referral by the presiding officer under, inter alia, the provisions of §§ 2.323 and 2.341.
Terms Used In 10 CFR 2.340
- Amendment: A proposal to alter the text of a pending bill or other measure by striking out some of it, by inserting new language, or both. Before an amendment becomes part of the measure, thelegislature must agree to it.
- Presiding officer: A majority-party Senator who presides over the Senate and is charged with maintaining order and decorum, recognizing Members to speak, and interpreting the Senate's rules, practices and precedents.
(2) Presiding officer initial decision and issuance of permit or license. (i) In a contested proceeding for the initial issuance or renewal of a construction permit, operating license, or renewed license, or the amendment of an operating or renewed license where the NRC has not made a determination of no significant hazards consideration, the Commission or the Director, Office of Nuclear Reactor Regulation, as appropriate, after making the requisite findings, shall issue, deny, or appropriately condition the permit or license in accordance with the presiding officer’s initial decision once that decision becomes effective.
(ii) In a contested proceeding for the amendment of a construction permit, operating license, or renewed license where the NRC has made a determination of no significant hazards consideration, the Commission or the Director, Office of Nuclear Reactor Regulation, as appropriate (appropriate official), after making the requisite findings and complying with any applicable provisions of § 2.1202(a) or § 2.1403(a), may issue the amendment before the presiding officer’s initial decision becomes effective. Once the presiding officer’s initial decision becomes effective, the appropriate official shall take action with respect to that amendment in accordance with the initial decision. If the presiding officer’s initial decision becomes effective before the appropriate official issues the amendment, then the appropriate official, after making the requisite findings, shall issue, deny, or appropriately condition the amendment in accordance with the presiding officer’s initial decision.
(b) Initial decision—combined license under 10 CFR part 52. (1) Matters in controversy; presiding officer consideration of matters not put in controversy by parties. In any initial decision in a contested proceeding on an application for a combined license under part 52 of this chapter (including an amendment to or renewal of combined license), the presiding officer shall make findings of fact and conclusions of law on the matters put into controversy by the parties and any matter designated by the Commission to be decided by the presiding officer. The presiding officer shall also make findings of fact and conclusions of law on any matter not put into controversy by the parties, but only to the extent that the presiding officer determines that a serious safety, environmental, or common defense and security matter exists, and the Commission approves of an examination of and decision on the matter upon its referral by the presiding officer under, inter alia, the provisions of §§ 2.323 and 2.341.
(2) Presiding officer initial decision and issuance of permit or license. (i) In a contested proceeding for the initial issuance or renewal of a combined license under part 52 of this chapter, or the amendment of a combined license where the NRC has not made a determination of no significant hazards consideration, the Commission or the Director, Office of Nuclear Reactor Regulation, as appropriate after making the requisite findings, shall issue, deny, or appropriately condition the permit or license in accordance with the presiding officer’s initial decision once that decision becomes effective.
(ii) In a contested proceeding for the amendment of a combined license under part 52 of this chapter where the NRC has made a determination of no significant hazards consideration, the Commission or the Director, Office of Nuclear Reactor Regulation, as appropriate (appropriate official), after making the requisite findings and complying with any applicable provisions of § 2.1202(a) or § 2.1403(a), may issue the amendment before the presiding officer’s initial decision becomes effective. Once the presiding officer’s initial decision becomes effective, the appropriate official shall take action with respect to that amendment in accordance with the initial decision. If the presiding officer’s initial decision becomes effective before the appropriate official issues the amendment, then the appropriate official, after making the requisite findings, shall issue, deny, or appropriately condition the amendment in accordance with the presiding officer’s initial decision.
(c) Initial decision on findings under 10 CFR 52.103 with respect to acceptance criteria in nuclear power reactor combined licenses. In any initial decision under § 52.103(g) of this chapter with respect to whether acceptance criteria have been or will be met, the presiding officer shall make findings of fact and conclusions of law on the matters put into controversy by the parties, and any matter designated by the Commission to be decided by the presiding officer. Matters not put into controversy by the parties, but identified by the presiding officer as matters requiring further examination, shall be referred to the Commission for its determination; the Commission may, in its discretion, treat any of these referred matters as a request for action under § 2.206 and process the matter in accordance with § 52.103(f) of this chapter.
(d) Initial decision—manufacturing license under 10 CFR part 52. (1) Matters in controversy; presiding officer consideration of matters not put in controversy by parties. In any initial decision in a contested proceeding on an application for a manufacturing license under subpart C of part 52 of this chapter (including an amendment to or renewal of a manufacturing license), the presiding officer shall make findings of fact and conclusions of law on the matters put into controversy by the parties and any matter designated by the Commission to be decided by the presiding officer. The presiding officer also shall make findings of fact and conclusions of law on any matter not put into controversy by the parties, but only to the extent that the presiding officer determines that a serious safety, environmental, or common defense and security matter exists, and the Commission approves of an examination of and decision on the matter upon its referral by the presiding officer under, inter alia, the provisions of §§ 2.323 and 2.341.
(2) Presiding officer initial decision and issuance of permit or license. (i) In a contested proceeding for the initial issuance or renewal of a manufacturing license under subpart C of part 52 of this chapter, or the amendment of a manufacturing license, the Commission or the Director, Office of Nuclear Reactor Regulation, as appropriate, after making the requisite findings, shall issue, deny, or appropriately condition the permit or license in accordance with the presiding officer’s initial decision once that decision becomes effective.
(ii) In a contested proceeding for the initial issuance or renewal of a manufacturing license under subpart C of part 52 of this chapter, or the amendment of a manufacturing license, the Commission or the Director, Office of Nuclear Reactor Regulation, as appropriate, may issue the license, permit, or license amendment in accordance with § 2.1202(a) or § 2.1403(a) before the presiding officer’s initial decision becomes effective. If, however, the presiding officer’s initial decision becomes effective before the license, permit, or license amendment is issued under § 2.1202 or § 2.1403, then the Commission or the Director, Office of Nuclear Reactor Regulation, as appropriate, shall issue, deny, or appropriately condition the license, permit, or license amendment in accordance with the presiding officer’s initial decision.
(e) Initial decision—other proceedings not involving production or utilization facilities—(1) Matters in controversy; presiding officer consideration of matters not put in controversy by parties. In a proceeding not involving production or utilization facilities, the presiding officer shall make findings of fact and conclusions of law on the matters put into controversy by the parties to the proceeding, and on any matters designated by the Commission to be decided by the presiding officer. Matters not put into controversy by the parties, but identified by the presiding officer as requiring further examination, must be referred to the Director, Office of Nuclear Material Safety and Safeguards. Depending on the resolution of those matters, the Director, Office of Nuclear Material Safety and Safeguards, after making the requisite findings, shall issue, deny, revoke or appropriately condition the license, or take other action as necessary or appropriate.
(2) Presiding officer initial decision and issuance of permit or license. (i) In a contested proceeding under this paragraph (e), the Commission or the Director, Office of Nuclear Material Safety and Safeguards, as appropriate, shall issue, deny, or appropriately condition the permit, license, or license amendment in accordance with the presiding officer’s initial decision once that decision becomes effective.
(ii) In a contested proceeding under this paragraph (e), the Commission or the Director, Office of Nuclear Material Safety and Safeguards, as appropriate, may issue the permit, license, or amendment in accordance with § 2.1202(a) or § 2.1403(a) before the presiding officer’s initial decision becomes effective. If, however, the presiding officer’s initial decision becomes effective before the permit, license, or amendment is issued under § 2.1202 or § 2.1403, then the Commission or the Director, Office of Nuclear Material Safety and Safeguards, as appropriate,shall issue, deny, or appropriately condition the permit, license, or amendment in accordance with the presiding officer’s initial decision.
(f) Immediate effectiveness of certain presiding officer decisions. A presiding officer’s initial decision directing the issuance or amendment of a limited work authorization under § 50.10 of this chapter, an early site permit under subpart A of part 52 of this chapter, a construction permit or construction authorization under part 50 of this chapter, an operating license under part 50 of this chapter, a combined license under subpart C of part 52 of this chapter, a manufacturing license under subpart F of part 52 of this chapter, a renewed license under part 54, or a license under part 72 of this chapter to store spent fuel in an independent spent fuel storage facility (ISFSI) or a monitored retrievable storage installation (MRS), an initial decision directing issuance of a license under part 61 of this chapter, or an initial decision under § 52.103(g) of this chapter that acceptance criteria in a combined license have been met, is immediately effective upon issuance unless the presiding officer finds that good cause has been shown by a party why the initial decision should not become immediately effective.
(g)-(h) [Reserved]
(i) Issuance of authorizations, permits, and licenses—production and utilization facilities. The Commission or the Director, Office of Nuclear Reactor Regulation, as appropriate, shall issue a limited work authorization under § 50.10 of this chapter, an early site permit under subpart A of part 52 of this chapter, a construction permit or construction authorization under part 50 of this chapter, an operating license under part 50 of this chapter, a combined license under subpart C of part 52 of this chapter, or a manufacturing license under subpart F of part 52 of this chapter within 10 days from the date of issuance of the initial decision:
(1) If the Commission or the Director has made all findings necessary for issuance of the authorization, permit or license, not within the scope of the initial decision of the presiding officer; and
(2) Notwithstanding the pendency of a petition for reconsideration under § 2.345, a petition for review under § 2.341, or a motion for stay under § 2.342, or the filing of a petition under § 2.206.
(j) Issuance of finding on acceptance criteria under 10 CFR 52.103. The Commission or the Director, Office of Nuclear Reactor Regulation, as appropriate, shall make the finding under 10 CFR 52.103(g) that acceptance criteria in a combined license are met within 10 days from the date of the presiding officer’s initial decision:
(1) If the Commission or the Director is otherwise able to make the finding under 10 CFR 52.103(g) that the prescribed acceptance criteria are met for those acceptance criteria not within the scope of the initial decision of the presiding officer;
(2) If the presiding officer’s initial decision—with respect to contentions that the prescribed acceptance criteria have not been met—finds that those acceptance criteria have been met, and the Commission or the Director thereafter is able to make the finding that those acceptance criteria are met;
(3) If the presiding officer’s initial decision—with respect to contentions that the prescribed acceptance criteria will not be met—finds that those acceptance criteria will be met, and the Commission or the Director thereafter is able to make the finding that those acceptance criteria are met; and
(4) Notwithstanding the pendency of a petition for reconsideration under 10 CFR 2.345, a petition for review under 10 CFR 2.341, or a motion for stay under 10 CFR 2.342, or the filing of a petition under 10 CFR 2.206.
(k) Issuance of other licenses. The Commission or the Director, Office of Nuclear Material Safety and Safeguards, as appropriate, shall issue a license, including a license under part 72 of this chapter to store spent fuel in either an independent spent fuel storage facility (ISFSI) located away from a reactor site or at a monitored retrievable storage installation (MRS), within 10 days from the date of issuance of the initial decision:
(1) If the Commission or the Director has made all findings necessary for issuance of the license, not within the scope of the initial decision of the presiding officer; and
(2) Notwithstanding the pendency of a petition for reconsideration under § 2.345, a petition for review under § 2.341, or a motion for stay under § 2.342, or the filing of a petition under § 2.206.