10 CFR 904.10 – Excess energy
(a) If excess Energy is determined by the United States to be available, it shall be made available to the Contractors, in accordance with the priority entitlement of section 105(a)(1)(C) of the Hoover Power Plant Act (43 U.S.C. § 619(a)(1)(c)). After the annual first- and second-priority entitlement to excess energy has been obligated for delivery, Western will make available one-third of the third-priority excess energy to the Arizona Power Authority, one-third to the Colorado River Commission of Nevada, and one-third to the California Contractors.
Terms Used In 10 CFR 904.10
- Entitlement: A Federal program or provision of law that requires payments to any person or unit of government that meets the eligibility criteria established by law. Entitlements constitute a binding obligation on the part of the Federal Government, and eligible recipients have legal recourse if the obligation is not fulfilled. Social Security and veterans' compensation and pensions are examples of entitlement programs.
(b) Western will make available third-priority excess energy to the California Contractors based on the following formula:
(c) The charge for all Excess Energy shall be the charge for Boulder Canyon Project Firm Energy existing at the time the Excess Energy is made available to the Contractor, including the appropriate Lower Basin Development Fund Contribution Charge.