(a) Baselines Required.—(1) In accordance with paragraph (2), the Director of the Missile Defense Agency shall establish and maintain an acquisition baseline for—

(A) each program element of the ballistic missile defense system, as specified in section 223 of this title; and

(B) each designated major subprogram of such program elements.


Ask a legal question, get an answer ASAP!
Click here to chat with a lawyer about your rights.

Terms Used In 10 USC 225

  • Assets: (1) The property comprising the estate of a deceased person, or (2) the property in a trust account.
  • Baseline: Projection of the receipts, outlays, and other budget amounts that would ensue in the future without any change in existing policy. Baseline projections are used to gauge the extent to which proposed legislation, if enacted into law, would alter current spending and revenue levels.
  • Contract: A legal written agreement that becomes binding when signed.
  • Fiscal year: The fiscal year is the accounting period for the government. For the federal government, this begins on October 1 and ends on September 30. The fiscal year is designated by the calendar year in which it ends; for example, fiscal year 2006 begins on October 1, 2005 and ends on September 30, 2006.
  • Oversight: Committee review of the activities of a Federal agency or program.

(2) The Director shall establish an acquisition baseline required by paragraph (1) before the date on which the program element or major subprogram enters—

(A) engineering and manufacturing development (or its equivalent); and

(B) production and deployment.


(3) Except as provided by subsection (d), the Director may not adjust or revise an acquisition baseline established under this section.

(b) Elements of Baselines.—Each acquisition baseline required by subsection (a) for a program element or major subprogram shall include the following:

(1) A comprehensive schedule, including—

(A) research and development milestones;

(B) acquisition milestones, including design reviews and key decision points;

(C) key test events, including ground, flight, and cybersecurity tests and ballistic missile defense system tests;

(D) delivery and fielding schedules;

(E) quantities of assets planned for acquisition and delivery in total and by fiscal year; and

(F) planned contract award dates.


(2) A detailed technical description of—

(A) the capability to be developed, including hardware and software;

(B) system requirements, including performance requirements;

(C) how the proposed capability satisfies a capability requirement or performance attribute identified through—

(i) the missile defense warfighter involvement process, as governed by United States Strategic Command Instruction 538-03, or such successor document; or

(ii) processes and products approved by the Joint Chiefs of Staff or Joint Requirements Oversight Council;


(D) key knowledge points that must be achieved to permit continuation of the program and to inform production and deployment decisions; and

(E) how the Director plans to improve the capability over time.


(3) A cost estimate, including—

(A) a life-cycle cost estimate that separately identifies the costs regarding research and development, procurement, military construction, operations and sustainment, and disposal;

(B) program acquisition unit costs for the program element;

(C) average procurement unit costs and program acquisition costs for the program element;

(D) an identification of when the document regarding the program joint cost analysis requirements description is scheduled to be approved; and

(E) an explanation for why a program joint cost analysis requirements description has not been prepared and approved, and, if a program joint cost analysis requirements description is not applicable, the rationale for such inapplicability.


(4) A test baseline summarizing the comprehensive test program for the program element or major subprogram outlined in the integrated master test plan.


(c) Annual Reports on Acquisition Baselines.—(1) Not later than February 15 of each year, the Director shall submit to the congressional defense committees a report on the acquisition baselines required by subsection (a).

(2)(A) The first report under paragraph (1) shall set forth each acquisition baseline required by subsection (a) for a program element or major subprogram.

(B) Each subsequent report under paragraph (1) shall include—

(i) any new acquisition baselines required by subsection (a) for a program element or major subprogram; and

(ii) with respect to an acquisition baseline that was previously included in a report under paragraph (1), an identification of any changes or variances made to the elements described in subsection (b) for such acquisition baseline, as compared to—

(I) the original acquisition baseline for such program element or major subprogram;

(II) the acquisition baseline for such program element or major subprogram that was submitted in the report during the previous year; and

(III) the most recent adjusted or revised acquisition baseline for such program element or major subprogram under subsection (d).


(3)(A) Each report under paragraph (1) shall include the total system costs for each element described in subparagraph (B) that comprises the missile defense system, without regard to funding source or management control (such as the Missile Defense Agency, a military department, or other element of the Department of Defense).

(B) The elements described in this subparagraph shall include the following:

(i) Research and development.

(ii) Procurement.

(iii) Military construction.

(iv) Operations and sustainment.

(v) Disposal.


(4) Each report under this subsection shall be submitted in unclassified form, but may include a classified annex.

(5) In this subsection:

(A) The term “original acquisition baseline” means, with respect to a program element or major subprogram, the first acquisition baseline created for the program element or major subprogram that has no previous iterations and has not been adjusted or revised, including any adjustments or revisions pursuant to subsection (d).

(B) The term “total system costs” means, with respect to each element that comprises the missile defense system—

(i) all combined costs from closed, canceled, and active acquisition baselines;

(ii) any costs shifted to or a part of future efforts without an established acquisition baseline; and

(iii) any costs under the responsibility of a military department or other Department entity.


(d) Exception to Limitation on Revision.—The Director may adjust or revise an acquisition baseline established under this section if the Director submits to the congressional defense committees notification of—

(1) a justification for such adjustment or revision;

(2) the specific adjustments or revisions made to the acquisition baseline, including to the elements described in subsection (b); and

(3) the effective date of the adjusted or revised acquisition baseline.


(e) Operations and Sustainment Cost Estimates.—The Director shall ensure that each life-cycle cost estimate included in an acquisition baseline pursuant to subsection (b)(3)(A) includes—

(1) all of the operations and sustainment costs for which the Director is responsible;

(2) a description of the operations and sustainment functions and costs for which a military department is responsible;

(3) the amount of operations and sustainment costs (dollar value and base year) for which the military department or other element of the Department of Defense is responsible; and

(4)(A) a citation to the source (such as a joint cost estimate or one or more military department estimates) that captures the operations and sustainment costs for which a military department or other element of the Department of Defense is responsible;

(B) the date the source was prepared; and

(C) if and when the source was independently verified by the Office for Cost Assessment and Program Evaluation.