24 CFR 882.507 – Completion of rehabilitation
(a) Notification of completion. The Owner must notify the PHA when the work is completed and submit to the PHA the evidence of completion and certifications described in paragraphs (b) and (c) of this section.
(b) Evidence of completion. Completion of the unit(s) must be evidenced by furnishing the PHA with the following:
(1) A certificate of occupancy and/or other official approvals as required by the locality.
(2) A certification by the Owner that:
(i) The unit(s) has been completed in accordance with the requirements of the Agreement;
(ii) The unit(s) is in good and tenantable condition;
(iii) The unit(s) has been rehabilitated in accordance with the applicable zoning, building, housing and other codes, ordinances or regulations, as modified by any waivers obtained from the appropriate officials;
(iv) The unit(s) are in compliance with part 35, subparts A, B, H, and R of this title.
(iv) Any unit(s) built prior to 1973 are in compliance with § 882.404(c)(3) and § 882.404(c)(4).
(v) If applicable, the Owner has complied with the provisions of the Agreement relating to the payment of not less than prevailing wage rates and that to the best of the Owner’s knowledge and belief there are no claims of underpayment concerning alleged violations of said provisions of the Agreement. In the event there are any such pending claims to the knowledge of the Owner, PHA or HUD, the Owner will be required to place sufficient amount in escrow, as determined by the PHA or HUD, to assure such payments.
(c) Actual cost and rehabilitation loan certifications. The Owner must provide the PHA with a certification of the costs incurred for the rehabilitation and any temporary relocation as well as the interest rate and term of any rehabilitation loan. The Owner must certify that these are the actual costs, interest rate, and term.
(d) Review and inspections. The PHA must review the evidence of completion for compliance with paragraph (b) of this section. The PHA also must inspect the unit(s) to be assisted to determine that the unit(s) has been completed in accordance with the Agreement and meets the Housing Quality Standards or other standards approved by HUD for the Program. If the inspection discloses defects or deficiencies, the inspector must report these in detail.
(e) Acceptance. (1) If the PHA determines from the review and inspection that the unit(s) has been completed in accordance with the Agreement, the unit(s) will be accepted.
(2) If there are any items of delayed completion which are minor items or which are incomplete because of weather conditions, and in any case which do not preclude or affect occupancy, and all other requirements of the Agreement have been met, the unit(s) must be accepted. An escrow fund determined by the PHA to be sufficient to assure completion for items of delayed completion must be required, as well as a written agreement between the PHA and the Owner, to be included as an exhibit to the Contract, specifying the schedule for completion. If the items are not completed within the agreed time period, the PHA may terminate the Contract or exercise other rights under the Contract.
(3) If other deficiencies exist, the PHA must determine whether and to what extent the deficiencies are correctable, and whether the Contract Rents should be reduced. The Owner must be notified of the PHA’s decision. If the corrections required by the PHA are possible, the PHA and the Owner must enter into an agreement for the correction of the deficiencies within a specified time. If the deficiencies are corrected within the agreed period of time, the PHA must accept the unit(s).
(4) Otherwise, the unit(s) may not be accepted, and the Owner must be notified with a statement of the reasons for nonacceptance.