36 CFR 51.57 – How does a concessioner request arbitration of the construction cost of a capital improvement?
Current as of: 2024 | Check for updates
|
Other versions
If a concessioner requests arbitration of the construction cost of a capital improvement determined by the Director, the request must be made in writing to the Director within 3 months of the date of the Director’s determination of construction cost under § 51.56. The arbitration procedures are described in § 51.51. The decision of the arbitration panel as to the construction cost of the capital improvement will be binding on the concessioner and the Director.
Terms Used In 36 CFR 51.57
- construction: as used in this part also means "install" or "installation" of fixtures where applicable. See 36 CFR 51.51