40 CFR 264.18 – Location standards
(a) Seismic considerations. (1) Portions of new facilities where treatment, storage, or disposal of hazardous waste will be conducted must not be located within 61 meters (200 feet) of a fault which has had displacement in Holocene time.
(2) As used in paragraph (a)(1) of this section:
(i) “Fault” means a fracture along which rocks on one side have been displaced with respect to those on the other side.
(ii) “Displacement” means the relative movement of any two sides of a fault measured in any direction.
(iii) “Holocene” means the most recent epoch of the Quaternary period, extending from the end of the Pleistocene to the present.
(b) Floodplains. (1) A facility located in a 100-year floodplain must be designed, constructed, operated, and maintained to prevent washout or any hazardous waste by a 100-year flood, unless the owner or operator can demonstrate to the Regional Administrator’s satisfaction that:
(i) Procedures are in effect which will cause the waste to be removed safely, before flood waters can reach the facility, to a location where the wastes will not be vulnerable to flood waters; or
(ii) For existing surface impoundments, waste piles, land treatment units, landfills, and miscellaneous units, no adverse effects on human health or the environment will result if washout occurs, considering:
(A) The volume and physical and chemical characteristics of the waste in the facility;
(B) The concentration of hazardous constituents that would potentially affect surface waters as a result of washout;
(C) The impact of such concentrations on the current or potential uses of and water quality standards established for the affected surface waters; and
(D) The impact of hazardous constituents on the sediments of affected surface waters or the soils of the 100- year floodplain that could result from washout.
(2) As used in paragraph (b)(1) of this section:
(i) “100-year floodplain” means any land area which is subject to a one percent or greater chance of flooding in any given year from any source.
(ii) “Washout” means the movement of hazardous waste from the active portion of the facility as a result of flooding.
(iii) “100-year flood” means a flood that has a one percent chance of being equalled or exceeded in any given year.
(c) Salt dome formations, salt bed formations, underground mines and caves. The placement of any noncontainerized or bulk liquid hazardous waste in any salt dome formation, salt bed formation, underground mine or cave is prohibited, except for the Department of Energy Waste Isolation Pilot Project in New Mexico.