40 CFR 76.14 – Monitoring, recordkeeping, and reporting
(a) A petition for an alternative emission limitation demonstration period under § 76.10(d) shall include the following information:
Terms Used In 40 CFR 76.14
- Baseline: Projection of the receipts, outlays, and other budget amounts that would ensue in the future without any change in existing policy. Baseline projections are used to gauge the extent to which proposed legislation, if enacted into law, would alter current spending and revenue levels.
(1) In accordance with § 76.10(d)(4), the following information:
(i) Documentation that the owner or operator solicited bids for a NO
(ii) A copy of the performance guarantee submitted by the vendor of the installed NO
(iii) Documentation describing the operational and combustion conditions that are the basis of the performance guarantee.
(iv) Certification by the primary vendor of the NO
(v) Certification by the designated representative that the owner(s) or operator installed technology that meets the requirements of § 76.10(a)(2).
(2) In accordance with § 76.10(d)(9), the following information:
(i) The operating conditions of the NO
(ii) Certification by the designated representative that the owner(s) or operator have achieved and are following the operating conditions, boiler modifications, and upgrades that formed the basis for the system design and performance guarantee;
(iii) Any planned equipment modifications and upgrades for the purpose of achieving the maximum NO
(iv) A list of any modifications or replacements of equipment that are to be done prior to the completion of the demonstration period for the purpose of reducing emissions of NO
(v) The parametric testing that will be conducted to determine the reason or reasons for the failure of the unit to achieve the applicable emission limitation and to verify the proper operation of the installed NO
(A) The owner or operator of the unit may add tests to those listed in § 76.15, if such additions provide data relevant to the failure of the installed NO
(B) The owner or operator of the unit may remove tests listed in § 76.15 that are shown, to the satisfaction of the permitting authority, not to be relevant to NO
(C) In the event the performance guarantee or the NO
(3) In accordance with § 76.10(d)(10), the following information for the operating period:
(i) The average NO
(ii) The highest hourly NO
(iii) Hourly NO
(iv) Total heat input (in mmBtu) for the unit for each hour of operation, calculated in accordance with the requirements of part 75 of this chapter; and
(v) Total integrated hourly gross unit load (in MWge).
(b) A petition for an alternative emission limitation shall include the following information in accordance with § 76.10(e)(6).
(1) Total heat input (in mmBtu) for the unit for each hour of operation, calculated in accordance with the requirements of part 75 of this chapter;
(2) Hourly NO
(3) Total integrated hourly gross unit load (MWge).
(c) Reporting of the costs of low NO
(2) The report under paragraph (c)(1) of this section is not required with regard to the following types of Group 1, Phase I units:
(i) Units employing no new NO
(ii) Units employing modifications to boiler operating parameters (e.g., burners out of service or fuel switching) without low NO
(iii) Units with wall-fired boilers employing only overfire air and units with tangentially fired boilers employing only separated overfire air; or
(iv) Units beginning installation of a new NO
(3) The report under paragraph (c)(1) of this section shall be submitted to the Administrator by:
(i) 120 days after completion of the low NO
(ii) May 23, 1995, if the project was completed on or before January 23, 1995.