(b) The Senior Procurement Executive (SPE) is authorized to make determinations that there is substantial evidence that contractors’ requests for advance, partial, or progress payments are based on fraud and may direct that further payments to the contractors be reduced or suspended, as provided in FAR 32.006.

Ask a legal question, get an answer ASAP!
Click here to chat with a lawyer about your rights.

Terms Used In 48 CFR 832.006-1

  • Evidence: Information presented in testimony or in documents that is used to persuade the fact finder (judge or jury) to decide the case for one side or the other.
  • Fraud: Intentional deception resulting in injury to another.

[83 FR 49305, Oct. 1, 2018]