(a) Requirement for Contractor To Provide Notice of Delays.—The Secretary of the Navy shall require prime contractors of any Navy procurement program funded under either the Shipbuilding and Conversion, Navy account or the Other Procurement, Navy account to report within 15 calendar days any stop work order or other manufacturing disruption of 15 calendar days or more, by the prime contractor or any subcontractor, to the respective program manager and Navy technical authority.

Ask a legal question, get an answer ASAP!
Click here to chat with a lawyer about your rights.

Terms Used In 10 USC 8751

  • Fiscal year: The fiscal year is the accounting period for the government. For the federal government, this begins on October 1 and ends on September 30. The fiscal year is designated by the calendar year in which it ends; for example, fiscal year 2006 begins on October 1, 2005 and ends on September 30, 2006.

(b) Quarterly Reports.—The Secretary of the Navy shall submit to the congressional defense committees not later than 15 calendar days after the end of each quarter of a fiscal year a report listing all notifications made pursuant to subsection (a) during the preceding quarter.