15 USC 3210 – Prior and pending proceedings
Current as of: 2024 | Check for updates
|
Other versions
For purposes of this chapter, proceedings commenced by any State regulatory authority (with respect to gas utilities for which it has ratemaking authority) and any nonregulated gas utility before November 9, 1978, and actions taken before such date in such proceedings shall be treated as complying with the requirements of this chapter if such proceedings and actions substantially conform to such requirements. For purposes of this chapter, any such proceeding or action commenced before November 9, 1978, but not completed before such date shall comply with the requirements of this chapter, to the maximum extent practicable, with respect to so much of such proceeding or action as takes place after such date.
Terms Used In 15 USC 3210
- State: means a State, the District of Columbia, the Commonwealth of Puerto Rico, or any other territory or possession of the United States. See 1 USC 7