(a) Each reclamation plan submitted as part of a permit application pursuant to the provisions of this article shall include, in the degree of detail necessary to demonstrate that reclamation required can be accomplished, a statement of:

Ask a real estate law question, get an answer ASAP!
Thousands of highly rated, verified real estate lawyers.
Specialties include: All Real Estate Law, Landlord and Tenant Law, Foreclosure, Homeowners' Association, Trespassing, Property Law, General Legal and more.
Click here to chat with a lawyer about your rights.

Terms Used In Alabama Code 9-16-84

  • following: means next after. See Alabama Code 1-1-1
  • state: when applied to the different parts of the United States, includes the District of Columbia and the several territories of the United States. See Alabama Code 1-1-1
(1) The identification of the lands subject to surface coal mining operations over the estimated life of those operations and the size, sequence, and timing of the sub-areas for which it is anticipated that individual permits for mining will be sought;
(2) The condition of the land to be covered by the permit prior to any mining including:

a. The uses existing at the time of the application, and if the land has a history of previous mining, the uses which preceded any mining; and
b. The capability of the land prior to any mining to support a variety of uses giving consideration to soil and foundation characteristics, topography, and vegetative cover, and, if applicable, a soil survey prepared pursuant to Section 9-16-83(b)(15); and
c. The productivity of the land prior to mining, including appropriate classification as prime farm lands, as well as the average yield of food, fiber, forage, or wood products from such lands obtained under high levels of management;
(3) The use which is proposed to be made of the land following reclamation, including a discussion of the utility and capacity of the reclaimed land to support a variety of alternative uses and the relationship of such use to existing land use policies and plans, and the comments of and owner of the surface, state and local governments or agencies thereof which would have to initiate, implement, approve or authorize the proposed use of the land following reclamation;
(4) A detailed description of how the proposed post-mining land use is to be achieved and the necessary support activities which may be needed to achieve the proposed land use;
(5) The engineering techniques proposed to be used in mining and reclamation and a description of the major equipment; a plan for the control of surface water drainage and of water accumulation; a plan, where appropriate, for backfilling, soil stabilization, and compacting, grading, and appropriate revegetation; a plan for soil reconstruction, replacement, and stabilization, pursuant to the performance standards for prime farm lands; an estimate of the cost per acre of the reclamation, including a statement as to how the permittee plans to comply with each of the requirements set out in Section 9-16-90;
(6) The consideration which has been given to maximize the utilization and conservation of the solid fuel resource being recovered so that reaffecting the land in the future can be minimized;
(7) A detailed estimated timetable for the accomplishment of each major step in the reclamation plan;
(8) The consideration which has been given to making the surface mining and reclamation operations consistent with surface owner plans, and applicable state and local land use plans and programs;
(9) The steps to be taken to comply with applicable air and water quality laws and regulations and any applicable health and safety standards;
(10) The consideration which has been given to developing the reclamation plan in a manner consistent with local, physical, environmental, and climatological conditions;
(11) All lands, interests in lands, or options on such interests held by the applicant or pending bids on interests in lands by the applicant, which lands are contiguous to the area to be covered by the permit;
(12) The results of test boring which the applicant has made at the area to be covered by the permit, or other equivalent information and data in a form satisfactory to the regulatory authority, including the location of subsurface water, and an analysis of the chemical properties including acid forming properties of the mineral and overburden; provided, that information which pertains only to the analysis of the chemical and physical properties of the coal (excepting information regarding such mineral or elemental contents which is potentially toxic in the environment) shall be kept confidential and not made a matter of public record;
(13) A detailed description of the measures to be taken during the mining and reclamation process to assure the protection of:

a. The quality of surface and ground water systems, both on and offsite, from adverse effects of the mining and reclamation process;
b. The rights of present users to such water; and
c. The quantity of surface and ground water systems, both on and offsite, from adverse effects of the mining and reclamation process or to provide alternative sources of water where such protection of quantity cannot be assured;
(14) Such other requirements as the regulatory authority shall prescribe by regulations.
(b) Any information required by this section shall be kept on file by the regulatory authority pursuant to Section 9-16-100.