All subcontractors bidding on contracts pursuant to this chapter shall be afforded the protections contained in Chapter 4 (commencing with Section 4100) of Part 1. The construction manager shall do all of the following:

(a) Provide public notice of the availability of work to be subcontracted in accordance with the publication requirements applicable to the competitive bidding process of the department.

Ask a legal question, get an answer ASAP!
Click here to chat with a lawyer about your rights.

Terms Used In California Public Contract Code 6705

(b) Provide a fixed date and time on which the subcontracted work will be awarded in accordance with the procedure established pursuant to this chapter

(c) Comply with any subcontracting procedures adopted by the department that were included in the department’s RFQ. If the department has adopted procedures to prequalify public works contractors, the construction manager may use the procedures to prequalify subcontractors.

(Added by Stats. 2012, Ch. 752, Sec. 1. (AB 2498) Effective January 1, 2013.)