In the case of a project described in subdivision (c) of Section 21065, the determination required by Section 21080.1 shall be made within 30 days from the date on which an application for a project has been received and accepted as complete by the lead agency. This period may be extended 15 days upon the consent of the lead agency and the project applicant.

(Amended by Stats. 1984, Ch. 586, Sec. 1.)

Ask a legal question, get an answer ASAP!
Click here to chat with a lawyer about your rights.