Failure of a contractor, or of an agent of a contractor, to pay or cause to be paid, in full or pro rata, the lawful claims of all persons, firms, association of persons or corporations (including surveyors and engineers), furnishing labor or material (including fuel), as required by § 3503 of this title, within 30 days after the receipt of any moneys or funds for the purposes of § 3502 of this title, shall be prima facie evidence of the payment, use or appropriation of such trust moneys or funds by the contractor in violation of the provisions of this chapter.

38 Del. Laws, c. 169, § ?3; Code 1935, § ?3654; 44 Del. Laws, c. 163, § ?3; 6 Del. C. 1953, § ?3504;

Ask a business law question, get an answer ASAP!
Thousands of highly rated, verified business lawyers.
Click here to chat with a lawyer about your rights.

Terms Used In Delaware Code Title 6 Sec. 3504

  • Appropriation: The provision of funds, through an annual appropriations act or a permanent law, for federal agencies to make payments out of the Treasury for specified purposes. The formal federal spending process consists of two sequential steps: authorization
  • Contractor: includes , but is not limited to, an architect, engineer, real estate broker or agent, subcontractor or other person, who enters into any contract with another person to furnish labor and/or materials in connection with the erection, construction, completion, alteration or repair of any building or for additions to a building, by such contractor, or for the sale to such other person of any lands and premises, whether owned by such contractor or another, upon which such contractor undertakes to erect, construct, complete, alter or repair any building or addition to a building. See Delaware Code Title 6 Sec. 3501
  • Evidence: Information presented in testimony or in documents that is used to persuade the fact finder (judge or jury) to decide the case for one side or the other.
  • Moneys or funds: includes , but is not limited to, the entire amount of all moneys or funds received by a contractor, as defined in this section, who, being the owner of the legal title to lands and premises, receives, in connection with a contract for the sale thereof and for the erection, construction, completion, alteration or repair of any building or addition thereon by such contractor, any moneys or funds by way of a loan or advance upon the security of such lands and premises for the purpose of such erection, construction, completion, alteration or repair, or who receives from the other contracting party or vendee any deposit or sum of money on account of the purchase or contract price, and no part of such moneys or funds shall be deemed or construed applicable to the payment of the cost or selling price of land, unless that part of the contract price or selling price applicable to cost or selling price of land, be specifically so stated in the contract. See Delaware Code Title 6 Sec. 3501