Florida Regulations 25-6.064: Extension of Facilities; Contribution in Aid of Construction
Current as of: 2024 | Check for updates
|
Other versions
(1) Application and scope. The purpose of this rule is to establish a uniform procedure by which investor-owned electric utilities calculate amounts due as contributions-in-aid-of-construction (CIAC) from customers who request new facilities or upgraded facilities in order to receive electric service, except as provided in Fl. Admin. Code R. 25-6.078
(2) Contributions-in-aid-of-construction for new or upgraded overhead facilities (CIACOH) shall be calculated as follows:
CIACOH
=
Total estimated work order job cost of installing the facilities
–
Four years expected
incremental base energy
revenue
–
Four years expected incremental base demand revenue, if applicable
(a) The cost of the service drop and meter shall be excluded from the total estimated work order job cost for new overhead facilities.
(b) The net book value and cost of removal, net of the salvage value, for existing facilities shall be included in the total estimated work order job cost for upgrades to those existing facilities.
(c) The expected annual base energy and demand charge revenues shall be estimated for a period ending not more than 5 years after the new or upgraded facilities are placed in service.
(d) In no instance shall the CIACOH be less than zero.
(3) Contributions-in-aid-of-construction for new or upgraded underground facilities (CIACUG) shall be calculated as follows:
CIACUG
=
CIACOH
+
Estimated difference between cost of providing the service underground and overhead
(4) Each utility shall apply the formula in subsections (2) and (3) of this rule uniformly to residential, commercial and industrial customers requesting new or upgraded facilities at any voltage level.
(5) The costs applied to the formula in subsections (2) and (3) shall be based on the requirements of Fl. Admin. Code R. 25-6.030, Storm Protection Plan, Fl. Admin. Code R. 25-6.034, Standard of Construction, Fl. Admin. Code R. 25-6.0341, Location of the Utility’s Electric Distribution Facilities, and Fl. Admin. Code R. 25-6.0345, Safety Standards for Construction of New Transmission and Distribution Facilities.
(6) All CIAC calculations under this rule shall be based on estimated work order job costs. In addition, each utility shall use its best judgment in estimating the total amount of annual revenues which the new or upgraded facilities are expected to produce.
(a) A customer may request a review of any CIAC charge within 12 months following the in-service date of the new or upgraded facilities. Upon request, the utility shall true-up the CIAC to reflect the actual costs of construction and actual base revenues received at the time the request is made.
(b) In cases where more customers than the initial applicant are expected to be served by the new or upgraded facilities, the utility shall prorate the total CIAC over the number of end-use customers expected to be served by the new or upgraded facilities within a period not to exceed 3 years, commencing with the in-service date of the new or upgraded facilities. The utility may require a payment equal to the full amount of the CIAC from the initial customer. For the 3-year period following the in-service date, the utility shall collect from those customers a prorated share of the original CIAC amount, and credit that to the initial customer who paid the CIAC. The utility shall file a tariff outlining its policy for the proration of CIAC.
(7) The utility may elect to waive all or any portion of the CIAC for customers, even when a CIAC is found to be applicable. If however, the utility waives a CIAC, the utility shall reduce net plant in service as though the CIAC had been collected, unless the Commission determines that there is a quantifiable benefit to the general body of ratepayers commensurate with the waived CIAC. Each utility shall maintain records of amounts waived and any subsequent changes that served to offset the CIAC.
(8) A detailed statement of its standard facilities extension and upgrade policies shall be filed by each utility as part of its tariffs. The tariffs shall have uniform application and shall be nondiscriminatory.
(9) If a utility and applicant are unable to agree on the CIAC amount, either party may appeal to the Commission for a review.
Rulemaking Authority Florida Statutes § 366.05(1), 350.127(2) FS. Law Implemented 366.03, 366.05(1), 366.06(1) FS. History-New 7-29-69, Amended 7-2-85, Formerly 25-6.64, Amended 2-1-07, 12-10-20.
Terms Used In Florida Regulations 25-6.064
- Appeal: A request made after a trial, asking another court (usually the court of appeals) to decide whether the trial was conducted properly. To make such a request is "to appeal" or "to take an appeal." One who appeals is called the appellant.
CIACOH
=
Total estimated work order job cost of installing the facilities
–
Four years expected
incremental base energy
revenue
–
Four years expected incremental base demand revenue, if applicable
(a) The cost of the service drop and meter shall be excluded from the total estimated work order job cost for new overhead facilities.
(b) The net book value and cost of removal, net of the salvage value, for existing facilities shall be included in the total estimated work order job cost for upgrades to those existing facilities.
(c) The expected annual base energy and demand charge revenues shall be estimated for a period ending not more than 5 years after the new or upgraded facilities are placed in service.
(d) In no instance shall the CIACOH be less than zero.
(3) Contributions-in-aid-of-construction for new or upgraded underground facilities (CIACUG) shall be calculated as follows:
CIACUG
=
CIACOH
+
Estimated difference between cost of providing the service underground and overhead
(4) Each utility shall apply the formula in subsections (2) and (3) of this rule uniformly to residential, commercial and industrial customers requesting new or upgraded facilities at any voltage level.
(5) The costs applied to the formula in subsections (2) and (3) shall be based on the requirements of Fl. Admin. Code R. 25-6.030, Storm Protection Plan, Fl. Admin. Code R. 25-6.034, Standard of Construction, Fl. Admin. Code R. 25-6.0341, Location of the Utility’s Electric Distribution Facilities, and Fl. Admin. Code R. 25-6.0345, Safety Standards for Construction of New Transmission and Distribution Facilities.
(6) All CIAC calculations under this rule shall be based on estimated work order job costs. In addition, each utility shall use its best judgment in estimating the total amount of annual revenues which the new or upgraded facilities are expected to produce.
(a) A customer may request a review of any CIAC charge within 12 months following the in-service date of the new or upgraded facilities. Upon request, the utility shall true-up the CIAC to reflect the actual costs of construction and actual base revenues received at the time the request is made.
(b) In cases where more customers than the initial applicant are expected to be served by the new or upgraded facilities, the utility shall prorate the total CIAC over the number of end-use customers expected to be served by the new or upgraded facilities within a period not to exceed 3 years, commencing with the in-service date of the new or upgraded facilities. The utility may require a payment equal to the full amount of the CIAC from the initial customer. For the 3-year period following the in-service date, the utility shall collect from those customers a prorated share of the original CIAC amount, and credit that to the initial customer who paid the CIAC. The utility shall file a tariff outlining its policy for the proration of CIAC.
(7) The utility may elect to waive all or any portion of the CIAC for customers, even when a CIAC is found to be applicable. If however, the utility waives a CIAC, the utility shall reduce net plant in service as though the CIAC had been collected, unless the Commission determines that there is a quantifiable benefit to the general body of ratepayers commensurate with the waived CIAC. Each utility shall maintain records of amounts waived and any subsequent changes that served to offset the CIAC.
(8) A detailed statement of its standard facilities extension and upgrade policies shall be filed by each utility as part of its tariffs. The tariffs shall have uniform application and shall be nondiscriminatory.
(9) If a utility and applicant are unable to agree on the CIAC amount, either party may appeal to the Commission for a review.
Rulemaking Authority Florida Statutes § 366.05(1), 350.127(2) FS. Law Implemented 366.03, 366.05(1), 366.06(1) FS. History-New 7-29-69, Amended 7-2-85, Formerly 25-6.64, Amended 2-1-07, 12-10-20.