(1) For the purposes of this section, reference to the “Clean Air Act” means 42 U.S.C. ss. 7401 et seq. as the same may hereinafter be amended and any related state or local legislation.
(2) Each public utility which owns or operates at least one electric generating unit affected by s. 404 or s. 405 of the Clean Air Act may submit, for commission approval, a plan to bring generating units into compliance with the Clean Air Act. A plan to implement compliance submitted by public utilities must include, at a minimum:

(a) The number and identity of affected generating units;

Ask a business law question, get an answer ASAP!
Thousands of highly rated, verified business lawyers.
Click here to chat with a lawyer about your rights.

Terms Used In Florida Statutes 366.825

  • Commission: means the Florida Public Service Commission. See Florida Statutes 366.02
  • Jurisdiction: (1) The legal authority of a court to hear and decide a case. Concurrent jurisdiction exists when two courts have simultaneous responsibility for the same case. (2) The geographic area over which the court has authority to decide cases.
  • Public utility: means every person, corporation, partnership, association, or other legal entity and their lessees, trustees, or receivers supplying electricity or gas (natural, manufactured, or similar gaseous substance) to or for the public within this state; but the term "public utility" does not include either a cooperative now or hereafter organized and existing under the Rural Electric Cooperative Law of the state; a municipality or any agency thereof; any dependent or independent special natural gas district; any natural gas transmission pipeline company making only sales or transportation delivery of natural gas at wholesale and to direct industrial consumers; any entity selling or arranging for sales of natural gas which neither owns nor operates natural gas transmission or distribution facilities within the state; or a person supplying liquefied petroleum gas, in either liquid or gaseous form, irrespective of the method of distribution or delivery, or owning or operating facilities beyond the outlet of a meter through which natural gas is supplied for compression and delivery into motor vehicle fuel tanks or other transportation containers, unless such person also supplies electricity or manufactured or natural gas. See Florida Statutes 366.02
(b) A description of the proposed action, and alternative actions considered by the public utility, to reduce sulfur dioxide emissions to levels required by the Clean Air Act at each affected unit;
(c) A description of the proposed action, and alternative actions considered by the public utility, to comply with nitrogen oxide emission rates required by the Clean Air Act at each affected unit;
(d) Estimated effects of the public utility’s proposed plan on the following:

1. Requirements for construction and operation of proposed or alternative facilities;
2. Achievable emissions reductions and methods for monitoring emissions;
3. The public utility’s proposed schedule for implements of compliance activities;
4. The estimated cost of implementation of the public utility’s compliance plan to the utility’s customers;
5. The public utility’s present and potential future sources of fuel; and
6. A statement of why the public utility’s proposed compliance plan is reasonable and in the public interest.
(e) A description of the proposed actions to comply with federal, state, and local requirements to implement the Clean Air Act.
(3) The commission shall review a plan to implement the Clean Air Act compliance submitted by public utilities pursuant to this section in order to determine whether such plans, the costs necessarily incurred in implementing such plans, and any effect on rates resulting from such implementation are in the public interest. The commission shall by order approve or disapprove plans to implement compliance submitted by public utilities within 8 months after the date of filing. Approval of a plan submitted by a public utility shall establish that the utility’s plan to implement compliance is prudent and the commission shall retain jurisdiction to determine in a subsequent proceeding that the actual costs of implementing the compliance plan are reasonable; provided, however, that nothing in this section shall be construed to interfere with the authority of the Department of Environmental Protection to determine whether a public utility is in compliance with ss. 403.087 and 403.0872 or the State Air Implementation Plan for the Clean Air Act.