Ask a business law question, get an answer ASAP!
Thousands of highly rated, verified business lawyers.
Click here to chat with a lawyer about your rights.

Terms Used In Florida Statutes 366.057

  • Commission: means the Florida Public Service Commission. See Florida Statutes 366.02
  • Public utility: means every person, corporation, partnership, association, or other legal entity and their lessees, trustees, or receivers supplying electricity or gas (natural, manufactured, or similar gaseous substance) to or for the public within this state; but the term "public utility" does not include either a cooperative now or hereafter organized and existing under the Rural Electric Cooperative Law of the state; a municipality or any agency thereof; any dependent or independent special natural gas district; any natural gas transmission pipeline company making only sales or transportation delivery of natural gas at wholesale and to direct industrial consumers; any entity selling or arranging for sales of natural gas which neither owns nor operates natural gas transmission or distribution facilities within the state; or a person supplying liquefied petroleum gas, in either liquid or gaseous form, irrespective of the method of distribution or delivery, or owning or operating facilities beyond the outlet of a meter through which natural gas is supplied for compression and delivery into motor vehicle fuel tanks or other transportation containers, unless such person also supplies electricity or manufactured or natural gas. See Florida Statutes 366.02
A public utility shall provide notice to the commission at least 90 days before the full retirement of an electrical power plant if the date of such retirement does not coincide with the retirement date in the public utility’s most recently approved depreciation study. No later than 90 days after such notice, the commission may schedule a hearing to determine whether retirement of the plant is prudent and consistent with the state’s energy policy goals in s. 377.601(2). At a hearing scheduled under this section, the utility shall present its proposed retirement date for the plant, remaining depreciation expense on the plant, any other costs to be recovered in relation to the plant, and any planned replacement capacity.