(1) As used in this section, the term:

(a) “Authority” has the same meaning as in s. 337.401(1)(a).

Ask a business law question, get an answer ASAP!
Thousands of highly rated, verified business lawyers.
Click here to chat with a lawyer about your rights.

Terms Used In Florida Statutes 366.99

  • Commission: means the Florida Public Service Commission. See Florida Statutes 366.02
  • Electric utility: means any municipal electric utility, investor-owned electric utility, or rural electric cooperative which owns, maintains, or operates an electric generation, transmission, or distribution system within the state. See Florida Statutes 366.02
  • Public utility: means every person, corporation, partnership, association, or other legal entity and their lessees, trustees, or receivers supplying electricity or gas (natural, manufactured, or similar gaseous substance) to or for the public within this state; but the term "public utility" does not include either a cooperative now or hereafter organized and existing under the Rural Electric Cooperative Law of the state; a municipality or any agency thereof; any dependent or independent special natural gas district; any natural gas transmission pipeline company making only sales or transportation delivery of natural gas at wholesale and to direct industrial consumers; any entity selling or arranging for sales of natural gas which neither owns nor operates natural gas transmission or distribution facilities within the state; or a person supplying liquefied petroleum gas, in either liquid or gaseous form, irrespective of the method of distribution or delivery, or owning or operating facilities beyond the outlet of a meter through which natural gas is supplied for compression and delivery into motor vehicle fuel tanks or other transportation containers, unless such person also supplies electricity or manufactured or natural gas. See Florida Statutes 366.02
  • Statute: A law passed by a legislature.
(b) “Facilities relocation” means the physical moving, modification, or reconstruction of public utility facilities to accommodate the requirements imposed by an authority.
(c) “Natural gas facilities” or “facilities” means gas mains, laterals, and service lines used to distribute natural gas to customers. The term includes all ancillary equipment needed for safe operations, including, but not limited to, regulating stations, meters, other measuring devices, regulators, and pressure monitoring equipment.
(d) “Natural gas facilities relocation costs” means the costs to relocate or reconstruct facilities as required by a mandate, a statute, a law, an ordinance, or an agreement between the utility and an authority, including, but not limited to, costs associated with reviewing plans provided by an authority. The term does not include any costs recovered through the public utility’s base rates.
(e) “Public utility” or “utility” has the same meaning as in s. 366.02, except that the term does not include an electric utility.
(2) A utility may submit to the commission, pursuant to commission rule, a petition describing the utility’s projected natural gas facilities relocation costs for the next calendar year, actual natural gas facilities relocation costs for the prior calendar year, and proposed cost-recovery factors designed to recover such costs. A utility’s decision to proceed with implementing a plan before filing such a petition does not constitute imprudence.
(3) The commission shall conduct an annual proceeding to determine each utility’s prudently incurred natural gas facilities relocation costs and to allow each utility to recover such costs through a charge separate and apart from base rates, to be referred to as the natural gas facilities relocation cost recovery clause. The commission’s review in the proceeding is limited to determining the prudence of the utility’s actual incurred natural gas facilities relocation costs and the reasonableness of the utility’s projected natural gas facilities relocation costs for the following calendar year, and providing for a true-up of the costs with the projections on which past factors were set. The commission shall require that any refund or collection made as a part of the true-up process includes interest.
(4) All costs approved for recovery through the natural gas facilities relocation cost recovery clause must be allocated to customer classes pursuant to the rate design most recently approved by the commission.
(5) If a capital expenditure is recoverable as a natural gas facilities relocation cost, the public utility may recover the annual depreciation on the cost, calculated at the public utility’s current approved depreciation rates, and a return on the undepreciated balance of the costs at the public utility’s weighted average cost of capital using the last approved return on equity.
(6) The commission shall adopt rules to implement and administer this section and shall propose a rule for adoption as soon as practicable after July 1, 2024.