Florida Statutes 713.07 – Priority of liens
Current as of: 2024 | Check for updates
|
Other versions
Terms Used In Florida Statutes 713.07
- Affidavit: A written statement of facts confirmed by the oath of the party making it, before a notary or officer having authority to administer oaths.
- Claim of lien: means the claim recorded as provided in…. See Florida Statutes 713.01
- Lien: A claim against real or personal property in satisfaction of a debt.
- Lienor: means a person who is:(a) A contractor;(b) A subcontractor;(c) A sub-subcontractor;(d) A laborer;(e) A materialman who contracts with the owner, a contractor, a subcontractor, or a sub-subcontractor; or(f) A professional lienor under…. See Florida Statutes 713.01
- Notice of commencement: means the notice recorded as provided in…. See Florida Statutes 713.01
- Owner: means a person who is the owner of any legal or equitable interest in real property, which interest can be sold by legal process, and who enters into a contract for the improvement of the real property. See Florida Statutes 713.01
(1) Liens under ss. 713.03 and 713.04 shall attach at the time of recordation of the claim of lien and shall take priority as of that time.(2) Liens under ss. 713.05 and 713.06 shall attach and take priority as of the time of recordation of the notice of commencement, but in the event a notice of commencement is not filed, then such liens shall attach and take priority as of the time the claim of lien is recorded.(3) All such liens shall have priority over any conveyance, encumbrance or demand not recorded against the real property prior to the time such lien attached as provided herein, but any conveyance, encumbrance or demand recorded prior to the time such lien attaches and any proceeds thereof, regardless of when disbursed, shall have priority over such liens.(4) If construction ceases or the direct contract is terminated before completion and the owner desires to recommence construction, he or she may pay all lienors in full or pro rata in accordance with s. 713.06(4) prior to recommencement in which event all liens for the recommenced construction shall take priority from such recommencement; or the owner may record an affidavit in the clerk’s office stating his or her intention to recommence construction and that all lienors giving notice have been paid in full except those listed therein as not having been so paid in which event 30 days after such recording, the rights of any person acquiring any interest, lien, or encumbrance on said property or of any lienor on the recommenced construction shall be paramount to any lien on the prior construction unless such prior lienor records a claim of lien within said 30-day period. A copy of said affidavit shall be served on each lienor named therein. Before recommencing, the owner shall record and post a notice of commencement for the recommenced construction, as provided in s. 713.13.