5 Guam Code Ann. § 5475
Current as of: 2023 | Check for updates
|
Other versions
Interest on amounts ultimately determined to be due to a contractor or Guam shall be payable at the statutory rate applicable to judgments from the date the claim arose through the date of decision or judgment, whichever is later.
105
COL 7/27/2023
5 Guam Code Ann. GOVERNMENT OPERATIONS
CH. 5 GUAM PROCUREMENT LAW
SOURCE: GC § 6977. MPC § 9-301.
2023 NOTE: Reference to “”Territory”” replaced with “”Guam”” pursuant to
1 Guam Code Ann. § 420.
2007 COMMENT: See 18 Guam Code Ann. § 47106 (Legal Rate of Interest).
———-
SUBARTICLE D
WAIVER OF SOVEREIGN IMMUNITY; LIMITATIONS ON
ACTIONS