Ask a business law question, get an answer ASAP!
Thousands of highly rated, verified business lawyers.
Click here to chat with a lawyer about your rights.

The commission may at any time, upon notice to the public utility affected, and after opportunity to be heard as provided in the case of complaints, rescind, alter or amend any order or decision made by it. Any order rescinding, altering or amending a prior order or decision shall, when served upon the public utility affected, have the same effect as is herein provided for original orders or decisions.