Sec. 7. All changes made in the designs or plans for a world war memorial are subject to the following:

(1) Changes must be agreed upon in writing, in advance, between the county executive and the contractor and architect.

Ask a legal question, get an answer ASAP!
Click here to chat with a lawyer about your rights.

Terms Used In Indiana Code 10-18-2-7

  • Contract: A legal written agreement that becomes binding when signed.
  • in writing: include printing, lithographing, or other mode of representing words and letters. See Indiana Code 1-1-4-5
  • Obligation: An order placed, contract awarded, service received, or similar transaction during a given period that will require payments during the same or a future period.
  • world war memorial: means :

    Indiana Code 10-18-2-1

(2) Compensation may not be paid for design or plan changes.

(3) Changes may not be made that will increase the total cost of the world war memorial.

(4) Changes may not affect the obligation of or release any surety or bondsmen on any contract or bond executed or given in connection with the building of the world war memorial. However, the liability shall be extended to embrace and cover the changes.

[Pre-2003 Recodification Citation: 10-7-1-7.]

As added by P.L.2-2003, SEC.9.