Indiana Code 14-26-8-48. Verified bill; partial payment; full payment
Current as of: 2024 | Check for updates
|
Other versions
Sec. 48. (a) A payment may not be made for work done under this chapter until a verified bill has been:
(2) approved by the surveyor;
(1) presented to the surveyor;
Terms Used In Indiana Code 14-26-8-48
- Affidavit: A written statement of facts confirmed by the oath of the party making it, before a notary or officer having authority to administer oaths.
- Verified: when applied to pleadings, means supported by oath or affirmation in writing. See Indiana Code 1-1-4-5
(3) filed with the auditor; and
(4) allowed by the commissioners.
(b) A partial payment may not be made to a contractor that exceeds seventy-five percent (75%) of the cost of the improvement.
(c) Full payment may not be made until:
(1) sixty-one (61) days after the completion and acceptance of the work; and
(2) after the contractor has filed with the surveyor an affidavit that all bills for labor, other service, or materials that have been used in the construction of or incorporated in the work have been paid in full.
[Pre-1995 Recodification Citation: 13-2-18-17 part.]
As added by P.L.1-1995, SEC.19.