Indiana Code 36-1-12-18. Change or alteration of specifications; change orders
Terms Used In Indiana Code 36-1-12-18
(c) A change order may not be issued before commencement of the actual construction, reconstruction, or repairs except in the case of an emergency. In that case, the board must make a declaration, and the board’s minutes must show the nature of the emergency.
(d) The total of all change orders issued that increase the scope of the project may not exceed twenty percent (20%) of the amount of the original contract. A change order issued as a result of circumstances that could not have been reasonably foreseen does not increase the scope of the project.
(e) All change orders must be directly related to the original public work project.
(f) If additional units of materials included in the original contract are needed, the cost of these units in the change order must be the same as those shown in the original contract.
As added by P.L.329-1985, SEC.24.