Sec. 9. (a) At least ten (10) days before the date fixed for a hearing under section 8 of this chapter, the engineer of the unit shall file with the works board an estimate of the maximum cost of the improvement proposed by the works board.

Ask a legal question, get an answer ASAP!
Click here to chat with a lawyer about your rights.

Terms Used In Indiana Code 36-9-36-9

  • Contract: A legal written agreement that becomes binding when signed.
     (b) The estimate must include the following:

(1) The cost of the guarantee under section 25 of this chapter.

(2) The cost of the maintenance of the improvements for at least three (3) years.

     (c) A unit may not enter into a contract under the preliminary resolution if the contract exceeds the engineer’s estimate filed under subsection (a).

As added by P.L.98-1993, SEC.7.