Sec. 1. (a) Except as provided in subsection (c), when design-build contracting is used for a public project, a public agency shall publish a notice of a request for qualifications under IC 5-3-1. The notice must allow at least fourteen (14) days for potential design-builders to respond to the request for qualifications.

Ask a legal question, get an answer ASAP!
Click here to chat with a lawyer about your rights.

     (b) Subsection (c) applies to a public project for which a public agency uses design-build contracting if:

(1) the public agency is a state educational institution; or

(2) the public agency is not a state educational institution and the preliminary estimated cost of the public project does not exceed five million dollars ($5,000,000).

     (c) A public agency that undertakes a public project to which this subsection applies may publish a notice of a combined request for qualifications and proposals under IC 5-3-1 that includes:

(1) the information otherwise required by this chapter; and

(2) a request for proposals as otherwise provided under IC 5-30-6.

The notice must allow at least thirty (30) days for potential design-builders to respond to the combined request for qualifications and proposals.

As added by P.L.74-2005, SEC.1. Amended by P.L.166-2011, SEC.7.