Sec. 12. (a) Subject to subsection (c), to qualify for the financial incentives set forth in section 13 of this chapter, a participating electricity supplier must obtain clean energy to meet the energy requirements of the participating electricity supplier‘s Indiana retail electric customers according to the following CPS goals:

(1) CPS Goal Period I: For the six (6) calendar years beginning January 1, 2013, and ending December 31, 2018, an average of at least four percent (4%) of the total electricity obtained by the participating electricity supplier to meet the energy requirements of its Indiana retail electric customers during the base year.

Ask a business law question, get an answer ASAP!
Thousands of highly rated, verified business lawyers.
Click here to chat with a lawyer about your rights.

Terms Used In Indiana Code 8-1-37-12

  • base year: means the calendar year ending December 31, 2010. See Indiana Code 8-1-37-1
  • CEC: means an interest that:

    Indiana Code 8-1-37-3

  • clean energy: means electricity that is produced from a clean energy resource. See Indiana Code 8-1-37-2
  • clean energy resource: means any of the following sources, clean sources, alternative technologies, or programs used in connection with the production or conservation of electricity:

    Indiana Code 8-1-37-4

  • commission: refers to the Indiana utility regulatory commission. See Indiana Code 8-1-1-1
  • CPS goal: refers to a goal set forth in section 12(a) of this chapter that a participating electricity supplier must achieve during a specified period during the program to qualify for one (1) or more of the financial incentives described in section 13 of this chapter. See Indiana Code 8-1-37-5
  • electricity supplier: means a public utility (as defined in IC 8-1-2-1) that furnishes retail electric service to customers in Indiana on January 1, 2011. See Indiana Code 8-1-37-6
  • participating electricity supplier: refers to an electricity supplier that has been approved by the commission under section 11 of this chapter to participate in the program. See Indiana Code 8-1-37-7
  • Year: means a calendar year, unless otherwise expressed. See Indiana Code 1-1-4-5
(2) CPS Goal Period II: For the six (6) calendar years beginning January 1, 2019, and ending December 31, 2024, an average of at least seven percent (7%) of the total electricity obtained by the participating electricity supplier to meet the energy requirements of its Indiana retail electric customers during the base year.

(3) CPS Goal Period III: In the calendar year ending December 31, 2025, at least ten percent (10%) of the total electricity obtained by the participating electricity supplier to meet the energy requirements of its Indiana retail electric customers during the base year.

     (b) For purposes of subsection (a), electricity is measured in megawatt hours. However, in determining whether a participating electricity supplier has met a CPS goal set forth in subsection (a), the commission shall require that at least fifty percent (50%) of the megawatt hours of clean energy obtained by the participating electricity supplier to meet the energy requirements of its Indiana retail electric customers during the CPS goal period under consideration must originate from clean energy resources located in Indiana.

     (c) In determining whether a participating electricity supplier has met a particular CPS goal set forth in subsection (a), the commission shall consider only clean energy that:

(1) except as provided in subsection (f), is obtained by the participating electricity supplier to meet the energy requirements of the participating electricity supplier’s Indiana retail electric customers during the CPS goal period under consideration; and

(2) is generated by a facility located in a control area that is part of a regional transmission organization of which an electricity supplier is a member.

     (d) An electricity supplier is not required to obtain clean energy to meet a particular CPS goal if the commission determines that the cost of clean energy resources available to the electricity supplier would result in an increase in the rates and charges of the electricity supplier that would not be just and reasonable.

     (e) A participating electricity supplier may own or purchase one (1) or more CECs to meet any of the CPS goals set forth in subsection (a) as long as the clean energy represented by the CEC meets the condition set forth in subsection (c)(2).

     (f) A participating electricity supplier may apply:

(1) amounts of clean energy supplied by the participating electricity supplier to its Indiana retail electric customers during a particular CPS goal period; or

(2) CECs acquired by the participating electricity supplier during a particular CPS goal period;

that exceed the requirements for the particular CPS goal period to the immediately succeeding CPS goal period.

     (g) A participating electricity supplier may use a clean energy resource described in section 4(a)(17) through 4(a)(21) of this chapter to satisfy not more than thirty percent (30%) of any of the CPS goals set forth in subsection (a).

As added by P.L.150-2011, SEC.16.