Indiana Code 8-1-40-15. Electricity supplier’s duty to procure customers’ excess distributed generation; amounts credited to customers to be recognized in fuel adjustment proceedings
Current as of: 2024 | Check for updates
|
Other versions
Terms Used In Indiana Code 8-1-40-15
- commission: refers to the Indiana utility regulatory commission created by IC 8-1-1-2. See Indiana Code 8-1-40-1
- customer: means a person that receives retail electric service from an electricity supplier. See Indiana Code 8-1-40-2
- distributed generation: means electricity produced by a generator or other device that is:
Indiana Code 8-1-40-3
- electricity supplier: means a public utility (as defined in IC 8-1-2-1) that furnishes retail electric service to customers in Indiana. See Indiana Code 8-1-40-4
- excess distributed generation: means the difference between:
Indiana Code 8-1-40-5
Sec. 15. An electricity supplier shall procure the excess distributed generation produced by a customer at a rate approved by the commission under section 17 of this chapter. Amounts credited to a customer by an electricity supplier for excess distributed generation shall be recognized in the electricity supplier’s fuel adjustment proceedings under IC 8-1-2-42.
As added by P.L.264-2017, SEC.6.