   Sec. 12. Any action to contest the validity of a public-private agreement or any underlying agreement related to the public-private project that is entered into under this article may not be brought after the fifteenth day following the publication of the notice of the designation of an operator under the public-private agreement as provided in section 11 of this chapter.

As added by P.L.47-2006, SEC.39. Amended by P.L.91-2014, SEC.25.