Sec. 8. As used in this chapter, “preconstruction services” means consulting to provide information regarding the impact of design on the construction services of a project, including:
(2) work sequencing;
(1) scheduling;
Terms Used In Indiana Code 8-23-9.5-8
- construction services: means the physical construction work undertaken by a CMGC or PDB to construct any portion of a project which may be awarded as a single contract for a project or multiple contracts for portions of a project. See Indiana Code 8-23-9.5-3
- project: means services provided using a two-phase contract with a CMGC or a PDB for preconstruction services and construction services to design, construct, alter, or repair:
Indiana Code 8-23-9.5-11
(3) cost engineering;
(4) constructability;
(5) cost estimates; and
(6) risk identification.